State: Odisha District: Sundargarh Block: Gurundia Gram Panchayat: Gurundia
Work Code: OD/373/3577/121582/385016/00045364 (Improvement & Maintenance of Kalyan Mandap at Gurundia)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Gurundia Proposal Date: -
Date of Commencement: 02-04-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Kalyan Mandap Project Type: Completion
Name of Executant: SANJAYA KUMAR PATEL
Administrative Approval Details
Approval No.: OD/373/3577/121582/385016/00045364/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3577/121582/385016/00045364/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 775000
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM006 BRM340 BRM028 BRM060 BRM052 BRM084 BRM104 BRM094 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Masonry Brick Work (AR0603ci) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 16.008 Cum 400 6403.2 0.672 10.757376 0.28 4.48224 - - - - - - - - - - - -
2 R.C.C. Work (AR0404Ac) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 14.73105 Cum - - 3.4733 51.165355965 0.45 6.6289725 0.36 5.303178 0.54 7.954767 0.045339 0.66789107595 0.041529 0.61176577545 - - - -
3 R.C.C. Work (AR0404Ad) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 3.3718 Cum - - 3.4733 11.71127294 0.45 1.51731 0.36 1.213848 0.54 1.820772 - - 0.0741335 0.2499633353 0.049542 0.1670457156 - -
4 R.C.C. Work (AR0404Ae) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Stairs excluding landing but including railing) 1.35 Cum - - 3.4733 4.688955 0.45 0.6075 0.36 0.486 0.54 0.729 - - 0.04806 0.064881 0.01494 0.020169 - -
5 R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 12.73125 Cum - - 3.4733 44.219450625 0.45 5.7290625 0.36 4.58325 0.54 6.874875 0.076659 0.97596489375 0.0502172 0.6393277275 - - - -
6 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 28.1 Qntl - - - - - - - - - - - - - - - - 1.05 29.505
Total Qty 6403.2 122.54241053 18.965085 11.586276 17.379414 1.6438559697 1.56593783825 0.1872147156 29.505
Rate Per Unit 0 0 110.25 409.5 409.5 0 0 0 0
Total Amount 0 0 2090.90062125 4744.580022 7116.870033 0 0 0 0
Total Royalty Amount (in Rs.): 13952.35067625