State: Odisha District: Khordha Block: Banapur Gram Panchayat: Gambharimunda
Work Code: OD/362/3458/119569/408334/00070328 (PRESERVATION AND DEVELOPMENT OF TANK AT KHAJURIA OF GAMBHARIMUNDA)
Project Category: Water Body
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Banapur Proposal Date: -
Date of Commencement: 07-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Preservation and Development of Water Bodies
Project Sub-Category: Tank Project Type: New Work
Name of Executant: pramoda kumar nanda
Administrative Approval Details
Approval No.: OD/362/3458/119569/408334/00070328/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3458/119569/408334/00070328/TS
Fund Sanction No.: 22569
Fund Sanction Amount (in Rs.): 663375
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM029 BRMMR0026 BRM079 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 57.2565696 Cum 2.29 131.117544384 0.48 27.483153408 0.96 54.966306816 - - - - - - - - - -
2 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 42.9424272 Cum - - - - - - - - - - - - - - - -
3 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 7.1570712 Cum - - - - - - 1 7.1570712 - - - - - - - -
4 Masonry Stone Work (AR0717i) :.Laterite stone masonry in cement mortar (1:6) in superstructure - Laterite stone masonry in cement mortar (1:6) in superstructure cost conveyance, royalty, taxes of all materials, labor, required for the work, etc. complete and as per direction of the Engineer-in-charge. 39.101491027853 Cum 0.572 22.366052867932 0.24 9.3843578466847 - - - - 1 39.101491027853 1 39.101491027853 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 189.800829 Sqm - - - - - - - - - - - - 0.00267 0.50676821343 0.126 23.914904454
6 Plastering (AR1008) :.20mm thick cement Plaster in CM (1:6) over brick work in inside. - 20mm thick cement Plaster in CM (1:6) for stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 116.5608790142 Sqm 0.057 6.6439701038094 0.021 2.4477784592982 - - - - - - - - - - - -
Total Qty 160.12756735574 39.315289713983 54.966306816 7.1570712 39.101491027853 39.101491027853 0.50676821343 23.914904454
Rate Per Unit 569.387 1108.49 1903.16 462.4 41.9 1526.79 58573.086 229.106
Total Amount 91174.555193984 43580.605495053 104609.67647994 3309.42972288 1638.352474067 59699.765486416 29682.978147302 5479.0480998381
Total Material Amount (in Rs.): 339174.41109948