State: Odisha District: Balasore Block: Baleshwar Gram Panchayat: Gud
Work Code: OD/346/3299/116070/392917/00060370 (Repair & Maintenance of Haraprasad Nodal UP School, Vill-Gudupahi, GP-Gudu)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Baleshwar Proposal Date: -
Date of Commencement: 11-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Primary School Building
Project Sub-Category: Elementary School Project Type: New Work
Name of Executant: K S ROSALIN
Administrative Approval Details
Approval No.: OD/346/3299/116070/392917/00060370/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3299/116070/392917/00060370/TS
Fund Sanction No.: 1198
Fund Sanction Amount (in Rs.): 166687
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM131 BRMMR0027 BRM340 BRM028 BRM138 BRM140
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 44.59344 Sqm - - - - - - - - - - - -
2 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 57.59986 Sqm 1 57.59986 1 57.59986 0.1375 7.91998075 0.015 0.8639979 - - - -
3 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 156.07704 Sqm - - - - 0.0358 5.587558032 0.015 2.3411556 - - - -
4 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 42.73538 Sqm - - - - 0.043 1.83762134 0.018 0.76923684 - - - -
5 Painting(AR0901a) :.Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 222.9672 Sqm - - - - - - - - 0.075 16.72254 - -
6 Painting(AR0919) :.Finishing wall One Coat with plastic emulsion paint of approved shades on old work (Inside) - Finishing wall One Coat with plastic emulsion paint of approved shades on old work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 222.9672 Sqm - - - - - - - - - - 0.075 16.72254
Total Qty 57.59986 57.59986 15.345160122 3.97439034 16.72254 16.72254
Rate Per Unit 660.6811111 8.5 570.467 548.19 155.32787 249.58787
Total Amount 38055.139504004 489.59881 8753.907459317 2178.7210404846 2597.4765191898 4173.7431395898
Total Material Amount (in Rs.): 56248.586472586