State: Odisha District: Sonepur Block: Tarbha Gram Panchayat: Tulunda
Work Code: OD/372/3571/275225/419719/00048418 (Construction of C.C road from Falsapadar UPS to Gaikhai Road)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Tarbha Proposal Date: -
Date of Commencement: 31-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: GOBARDHAN MEHER
Administrative Approval Details
Approval No.: OD/372/3571/275225/419719/00048418/AS
Technical Sanction Details
Technical Sanction No.: OD/372/3571/275225/419719/00048418/TS
Fund Sanction No.: 34188
Fund Sanction Amount (in Rs.): 500000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM084 BRM104
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 36 Cum 1 36 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 36 Cum - - 2.29 82.44 0.48 17.28 0.96 34.56 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 25.2 Cum - - 3.23 81.396 0.45 11.34 - - 0.9 22.68 - - - -
5 R.C.C. Work (AR0410d) :.Third floor - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 54 Sqm - - - - - - - - - - 0.95451428571429 51.543771428571 0.0089691428571429 0.48433371428571
Total Qty 36 163.836 28.62 34.56 22.68 51.543771428571 0.48433371428571
Rate Per Unit 413.05 546.172 417.99 1336.36 1656.01 297.726 58620.646
Total Amount 14869.8 89482.635792 11962.8738 46184.6016 37558.3068 15345.920892343 28391.955211008
Total Material Amount (in Rs.): 243796.09409535