State: Odisha District: Jharsuguda Block: Laikera Gram Panchayat: Sahaspur
Work Code: OD/357/3407/118557/381197/00049307 (IMPROVEMENT OF MARKET COMPLEX ,SAHASPUR)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Laikera Proposal Date: -
Date of Commencement: 17-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Market Complex Project Type: Upgradation or Improvement
Name of Executant: Diptee Nayak
Administrative Approval Details
Approval No.: OD/357/3407/118557/381197/00049307/AS
Technical Sanction Details
Technical Sanction No.: OD/357/3407/118557/381197/00049307/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Highly-Skilled Semi-Skilled
562 462 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 5.76069 Cubic Meter 3.9 22.466691 - - 0.18 1.0369242 - -
2 Plastering (AR1004) : First Floor - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 88.985 Square Meter 0.1236 10.998546 - - 0.1442 12.831637 - -
3 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 228.731 Square Meter 0.24 54.89544 - - 0.16 36.59696 - -
4 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 77.0215 Square Meter 0.17 13.093655 - - 0.14 10.78301 - -
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 79.9225 Square Meter 0.36 28.7721 - - - - 0.13 10.389925
7 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 7.1 Quintal 6.3976377952756 45.423228346457 1.9685039370079 13.976377952756 3.9370078740157 27.952755905512 3.4448818897638 24.458661417323
8 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 424.19 Square Meter 0.053763440860215 22.805913978495 - - - - 0.053763440860215 22.805913978495
Total Qty 89.201287105512 198.45557432495 57.654500395817 13.976377952756
Rate Per Man Day 562 462 612 512
Total Amount 50131.123353298 91686.475338128 35284.55424224 7155.905511811
Total Labour Amount (in Rs.): 184258.05844548