State: Odisha District: Mayurbhanj Block: Sukruli Gram Panchayat: Chaturanjali
Work Code: OD/365/3508/120359/388742/00037621 (Repair & renovation of Talangaon Haat at Talanga.)
Project Category: Other Infrastructure
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Sukruli Proposal Date: -
Date of Commencement: 23-02-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Rural Haat Project Type: New Work
Name of Executant: Nanda Kishore Soren
Administrative Approval Details
Approval No.: OD/365/3508/120359/388742/00037621/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3508/120359/388742/00037621/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 500000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
462 562 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 26.5248 Cubic Meter 0.516 13.6867968 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 45.19755 Cubic Meter 0.1236 5.58641718 - - - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 18.864225 Cubic Meter 3.9 73.5704775 - - 0.18 3.3955605 - -
4 Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 22.581 Cubic Meter 2.96 66.83976 - - 1.05 23.71005 0.35 7.90335
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.3 Cubic Meter 4.6 1.38 - - 0.68 0.204 - -
6 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 47.196 Square Meter 0.12 5.66352 - - 0.14 6.60744 - -
7 Flooring (AR0802i) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG crusher broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG crusher broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 100.1925 Square Meter 0.36 36.0693 - - - - 0.13 13.025025
8 Iron Work (AR1701) : Labour for hoisting joints, trusses and placing in position - Labour for hoisting joints, trusses and placing in position with all cost of labour and machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 70.56 Quintal 0.33464566929134 23.612598425197 1.9685039370079 138.89763779528 - - - -
9 Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 136.152 Square Meter 0.21505376344086 29.28 - - - - 0.16129032258065 21.96
10 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 47.196 Square Meter 0.11776344086022 5.5579633548387 - - - - 0.10776344086022 5.0860033548387
Total Qty 261.24683326004 33.9170505 47.974378354839 138.89763779528
Rate Per Man Day 462 562 612 512
Total Amount 120696.03696614 19061.382381 29360.319553161 71115.590551181
Total Labour Amount (in Rs.): 240233.32945148