State: Odisha District: Sambalpur Block: Jamankira Gram Panchayat: Badmal
Work Code: OD/371/3560/121311/381883/00075120 (Maint. Of market Complex At Badmal)
Project Category: Building
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Jamankira Proposal Date: -
Date of Commencement: 16-01-2026 Date of Completion: 23-02-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Market Complex Project Type: Repair and Maintenance
Name of Executant: BIDYA TUDU
Administrative Approval Details
Approval No.: OD/371/3560/121311/381883/00075120/AS
Technical Sanction Details
Technical Sanction No.: OD/371/3560/121311/381883/00075120/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 500000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
462 562 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Dismantling (AR1626) : Dismantling and removing marble chips flooring - Dismantling and removing marble chips flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 37.5 Square Meter 0.24193548387097 9.0725806451613 - - - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.4 Cubic Meter 3.9 56.16 - - 0.18 2.592 - -
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 6 Cubic Meter 4.6 27.6 - - 0.68 4.08 - -
4 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 23.5 Square Meter 0.24 5.64 - - 0.16 3.76 - -
5 Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 25.08 Square Meter 0.325 8.151 0.76 19.0608 - - 0.325 8.151
6 Flooring (AR0817ac) : First floor - Fixing Vitrified industrial Tile of premium grade having thickness 8mm to 10mm confirming to IS 4457 of size 300mmx300mm in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 56 Square Meter 0.34125 19.11 0.798 44.688 - - 0.34125 19.11
7 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 96.6 Square Meter 0.057 5.5062 - - 0.05 4.83 - -
8 Painting (AR0918g) : Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work .(Outside) - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 83.67 Square Meter 0.11776344086022 9.8532670967742 - - - - 0.10776344086022 9.0165670967742
9 Roofing (AR1135i) : G.C.I. Sheet (0.40mm thick) in walling - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in walling including cost of nuts and bolts, fitting, labour and material etc. complete as per direction of Engineer-in-Charge. 56 Square Meter 0.21505376344086 12.043010752688 - - - - 0.16129032258065 9.0322580645161
10 Iron Work (AR1703) : Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 12 Quintal 4.9212598425197 59.055118110236 1.9685039370079 23.622047244094 4.4291338582677 53.149606299213 - -
Total Qty 212.19117660486 68.411606299213 45.30982516129 87.370847244094
Rate Per Man Day 462 562 612 512
Total Amount 98032.323591445 38447.322740157 27729.61299871 44733.873788976
Total Labour Amount (in Rs.): 208943.13311929