State: Odisha District: Balasore Block: Basta Gram Panchayat: Natakata
Work Code: OD/346/3301/116130/392348/00064184 (IMPROVEMENT OF ROAD FROM BASANTAPUR CHHAK ROAD ADIVASI SAHI TO RABINDRA DEY HOUSE WITH GUARDWALL)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Basta Proposal Date: 08-06-2021
Date of Commencement: 17-02-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: BHAGYALAXMI MOHANTA
Administrative Approval Details
Approval No.: OD/346/3301/116130/392348/00064184/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3301/116130/392348/00064184/TS
Fund Sanction No.: 9122
Fund Sanction Amount (in Rs.): 254824
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 83.36359732 Cubic Meter 1.0600706713781 88.371304579505 - - - -
3 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 8.1552384 Cubic Meter 0.516 4.2081030144 - - - -
4 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 1.345614336 Cubic Meter 0.1236 0.1663179319296 - - - -
5 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 8.576592384 Cubic Meter 3.9 33.4487102976 - - 0.18 1.54378662912
6 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 23.72371008 Square Meter - - 0.05 1.186185504 0.05 1.186185504
Total Qty 126.19443582343 2.72997213312 1.186185504
Rate Per Man Day 462 562 512
Total Amount 58301.829350427 1534.2443388134 607.326978048
Total Labour Amount (in Rs.): 60443.400667288