State: Odisha District: Mayurbhanj Block: Karanjia Gram Panchayat: Bala
Work Code: OD/365/3498/120219/388856/00038459 (Development of weekly Rural Hat at Diajodi)
Project Category: Other Infrastructure
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Karanjia Proposal Date: -
Date of Commencement: 19-02-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Development of Rural Haat
Project Sub-Category: Rural Haat Project Type: New Work
Name of Executant: PRATAP
Administrative Approval Details
Approval No.: OD/365/3498/120219/388856/00038459/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3498/120219/388856/00038459/TS
Fund Sanction No.: 26763
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
462 562 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.81 Cubic Meter 0.516 18.99396 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 59.0895 Cubic Meter 0.1236 7.3034622 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 57.852 Cubic Meter 3.9 225.6228 - - 0.18 10.41336 - -
4 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 47.63 Square Meter 0.17 8.0971 - - 0.14 6.6682 - -
5 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 47.63 Square Meter 0.11776344086022 5.609072688172 - - - - 0.10776344086022 5.132772688172
6 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 166 Square Meter - - 0.05 8.3 0.05 8.3 - -
7 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.14 Cubic Meter 4.6 60.444 - - 0.68 8.9352 - -
8 Iron Work (AR1703) : Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 21.86064 Quintal 4.9212598425197 107.58188976378 1.9685039370079 43.032755905512 4.4291338582677 96.823700787402 - -
Total Qty 433.65228465195 131.1404607874 5.132772688172 51.332755905512
Rate Per Man Day 462 562 612 512
Total Amount 200347.3555092 73700.93896252 3141.2568851613 26282.371023622
Total Labour Amount (in Rs.): 303471.9223805