State: Odisha District: Balangir Block: Bangomunda Gram Panchayat: Kansil
Work Code: OD/345/3286/275183/421324/00038513 (Repair and maintenance of Primary School at Dumermunda)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Bangomunda Proposal Date: -
Date of Commencement: 31-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Primary School Building
Project Sub-Category: Elementary School Project Type: Repair and Maintenance
Name of Executant: SINGRAI MURMU
Administrative Approval Details
Approval No.: OD/345/3286/275183/421324/00038513/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3286/275183/421324/00038513/TS
Fund Sanction No.: 34989
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Dismantling (AR1612) : Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. Sqm 73.50949875 100.34838709677 7376.5596358545
2 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) Sqm 52.118583 997.5275381386 51989.721791262
3 Flooring (AR0816) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. Sqm 17.48898975 1172.8129760438 20511.314116697
4 Flooring (AR0817b) : Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. Sqm 23.674006975 867.670754651 20541.243497611
5 Plastering (AR1004i) : 12mm thick cement plaster (1:6) over Brick work in outside. - 12mm thick cement plster (1:6) over Brick work in outside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. Sqm 39.50700075 165.7232093752 6547.2269570784
6 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. Sqm 30.21670075 239.147688092 7226.2541261303
7 Painting (AR0920a) : Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) Sqm 207.8704625 163.75298201751 34039.408107734
8 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) Sqm 230.84444537 156.86604451751 36211.65504403
9 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) Cum 0.42050448 5290.6385201252 2224.7371997732
10 Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. Sqm 4.89970422 1517.605754651 7435.8193203598
11 Flooring (AR0816jk) : Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (For repair and maintenance). - Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the Chequred tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . Sqm 11.984487 964.1798009428 11555.200290062
12 Painting (AR0903ik) : Painting two coats of enamel paint in outer surface paint (outer surface)(For repair and maintenance) . - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside)(For repair and maintenance). Sqm 45.2727931875 167.00067737581 7560.5871290075
13 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. Qntl 1.0125 15758.174347087 15955.151526426
Total Amount (in Rs.): 229174.87874203
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Semi-Skilled Skilled
462 612 512 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Dismantling (AR1612) : Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 73.50949875 Square Meter 0.21505376344086 15.808494354839 - - - - - -
2 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 52.118583 Square Meter 0.216 11.257613928 - - - - 0.216 11.257613928
3 Flooring (AR0816) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 17.48898975 Square Meter 0.216 3.777621786 0.55 9.6189443625 - - 0.216 3.777621786
4 Flooring (AR0817b) : Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. 23.674006975 Square Meter 0.325 7.694052266875 - - - - 0.325 7.694052266875
5 Plastering (AR1004i) : 12mm thick cement plaster (1:6) over Brick work in outside. - 12mm thick cement plster (1:6) over Brick work in outside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 39.50700075 Square Meter 0.12 4.74084009 - - 0.14 5.530980105 - -
6 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 30.21670075 Square Meter 0.24 7.25200818 - - 0.16 4.83467212 - -
7 Painting (AR0920a) : Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 207.8704625 Square Meter 0.11776344086022 24.479540917204 - - - - 0.10776344086022 22.400836292204
8 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 230.84444537 Square Meter 0.11776344086022 27.185036190239 - - - - 0.10776344086022 24.876591736539
9 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 0.42050448 Cubic Meter 1.3333 0.560658623184 0.0573 0.024094906704 0.1 0.042050448 - -
10 Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 4.89970422 Square Meter 0.325 1.5924038715 0.76 3.7237752072 - - 0.325 1.5924038715
11 Flooring (AR0816jk) : Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (For repair and maintenance). - Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the Chequred tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . 11.984487 Square Meter 0.216 2.588649192 0.55 6.59146785 - - 0.216 2.588649192
12 Painting (AR0903ik) : Painting two coats of enamel paint in outer surface paint (outer surface)(For repair and maintenance) . - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside)(For repair and maintenance). 45.2727931875 Square Meter 0.12064516129032 5.4619434361694 - - - - 0.13709677419355 6.2067539047379
13 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 1.0125 Quintal 6.3976377952756 6.4776082677165 1.9685039370079 1.9931102362205 3.9370078740157 3.9862204724409 3.4448818897638 3.4879429133858
Total Qty 118.87647110373 83.882465891242 21.951392562624 14.393923145441
Rate Per Man Day 462 612 512 562
Total Amount 54920.929649922 51336.06912544 11239.112992064 8089.3848077378
Total Labour Amount (in Rs.): 125585.49657516
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM174 BRM340 BRM028 BRM131 BRMMR0027 BRM130 BRM129 BRM140 BRM252 BRM255 BRM060 BRM052 BRM134 BRM141 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 73.50949875 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 52.118583 Sqm 0.0076 0.3961012308 0.1074 5.5975358142 0.021 1.094490243 1 52.118583 - - - - - - - - - - - - - - - - - - - - - -
3 Flooring (AR0816) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 17.48898975 Sqm - - 0.2737 4.786736494575 0.013 0.22735686675 - - 1 17.48898975 1 17.48898975 - - - - - - - - - - - - - - - - - -
4 Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. 23.674006975 Sqm - - 0.1375 3.2551759590625 0.015 0.355110104625 - - - - - - 1 23.674006975 - - - - - - - - - - - - - - - -
5 Plastering (AR1004i) :.12mm thick cement plaster (1:6) over Brick work in outside. - 12mm thick cement plster (1:6) over Brick work in outside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 39.50700075 Sqm - - 0.0358 1.41435062685 0.015 0.59260501125 - - - - - - - - - - - - - - - - - - - - - - - -
6 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 30.21670075 Sqm - - 0.043 1.29931813225 0.018 0.5439006135 - - - - - - - - - - - - - - - - - - - - - - - -
7 Painting(AR0920a) :.Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 207.8704625 Sqm - - - - - - - - - - - - - - 0.125 25.9838078125 0.084 17.46111885 - - - - - - - - - - - -
8 Painting(AR0918ca) :.Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 230.84444537 Sqm - - - - - - - - - - - - - - - - 0.084 19.39093341108 0.125 28.85555567125 - - - - - - - - - -
9 R.C.C. Work (AR0404A) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 0.42050448 Cum - - 3.4733 1.460538210384 0.45 0.189227016 - - - - - - - - - - - - - - 0.36 0.1513816128 0.54 0.2270724192 - - - - - -
10 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 4.89970422 Sqm - - 0.1375 0.67370933025 0.015 0.0734955633 1 4.89970422 1 4.89970422 - - - - - - - - - - - - - - - - - - - -
11 Flooring (AR0816jk) :.Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (For repair and maintenance). - Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the Chequred tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . 11.984487 Sqm - - 0.2737 3.2801540919 0.013 0.155798331 - - 1 11.984487 - - - - - - - - - - - - - - 1 11.984487 - - - -
12 Painting(AR0903ik) :.Painting two coats of enamel paint in outer surface paint (outer surface)(For repair and maintenance) . - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside)(For repair and maintenance). 45.2727931875 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - 0.125 5.6590991484375 - -
13 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 1.0125 Qntl - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 1.0125
Total Qty 0.3961012308 21.767518659471 3.231983749425 57.01828722 34.37318097 17.48898975 23.674006975 25.9838078125 36.85205226108 28.85555567125 0.1513816128 0.2270724192 11.984487 5.6590991484375 1.0125
Rate Per Unit 2047.912 534.912 417.99 662.3175001 8.5 461.3175001 416.4375001 249.64732 125.80732 195.09732 1741.11 1723.4 254.75 205.64732 6206.132
Total Amount 811.18046377009 11643.706941175 1350.9368874222 37764.209451534 292.172038245 8067.9770307445 9858.744282019 6486.7879837857 4636.2579314664 5629.6415785717 263.57203986221 391.33660724928 3053.04806325 1163.7785734905 6283.70865
Total Material Amount (in Rs.): 97697.058522586
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM174 BRM340 BRM028 BRM131 BRM130 BRM129 BRM140 BRM252 BRM255 BRM060 BRM052 BRM141 BRM341
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 73.50949875 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 52.118583 Sqm 0.0076 0.3961012308 0.1074 5.5975358142 0.021 1.094490243 1 52.118583 - - - - - - - - - - - - - - - - - -
3 Flooring (AR0816) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 17.48898975 Sqm - - 0.2737 4.786736494575 0.013 0.22735686675 - - 1 17.48898975 - - - - - - - - - - - - - - - -
4 Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. 23.674006975 Sqm - - 0.1375 3.2551759590625 0.015 0.355110104625 - - - - 1 23.674006975 - - - - - - - - - - - - - -
5 Plastering (AR1004i) :.12mm thick cement plaster (1:6) over Brick work in outside. - 12mm thick cement plster (1:6) over Brick work in outside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 39.50700075 Sqm - - 0.0358 1.41435062685 0.015 0.59260501125 - - - - - - - - - - - - - - - - - - - -
6 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 30.21670075 Sqm - - 0.043 1.29931813225 0.018 0.5439006135 - - - - - - - - - - - - - - - - - - - -
7 Painting(AR0920a) :.Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat oil bound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 207.8704625 Sqm - - - - - - - - - - - - 0.125 25.9838078125 0.084 17.46111885 - - - - - - - - - -
8 Painting(AR0918ca) :.Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 230.84444537 Sqm - - - - - - - - - - - - - - 0.084 19.39093341108 0.125 28.85555567125 - - - - - - - -
9 R.C.C. Work (AR0404A) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 0.42050448 Cum - - 3.4733 1.460538210384 0.45 0.189227016 - - - - - - - - - - - - 0.36 0.1513816128 0.54 0.2270724192 - - - -
10 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 4.89970422 Sqm - - 0.1375 0.67370933025 0.015 0.0734955633 1 4.89970422 - - - - - - - - - - - - - - - - - -
11 Flooring (AR0816jk) :.Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (For repair and maintenance). - Fixing Chequred Tiles in floor, treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the Chequred tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . 11.984487 Sqm - - 0.2737 3.2801540919 0.013 0.155798331 - - - - - - - - - - - - - - - - - - - -
12 Painting(AR0903ik) :.Painting two coats of enamel paint in outer surface paint (outer surface)(For repair and maintenance) . - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside)(For repair and maintenance). 45.2727931875 Sqm - - - - - - - - - - - - - - - - - - - - - - 0.125 5.6590991484375 - -
13 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 1.0125 Qntl - - - - - - - - - - - - - - - - - - - - - - - - 1 1.0125
Total Qty 0.3961012308 21.767518659471 3.231983749425 57.01828722 17.48898975 23.674006975 25.9838078125 36.85205226108 28.85555567125 0.1513816128 0.2270724192 5.6590991484375 1.0125
Rate Per Unit 0 0 86.25 0 0 0 0 0 0 230.5 230.5 0 0
Total Amount 0 0 278.75859838791 0 0 0 0 0 0 34.8934617504 52.3401926256 0 0
Total Royalty Amount (in Rs.): 365.99225276391
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for PH Work @ Rs. 53000 Rs. 53000
2 Provision for Contingency @ 1% Rs. 2291.7487874203
3 Display Citizen Board @ Rs. 3000 Rs. 3000
4 Any Other Lumpsum @ Rs. 12533 Rs. 12533
Total Addition Component Amount (in Rs.): 70824.74878742
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 299999.62752945