State: Odisha District: Balasore Block: Bahanaga Gram Panchayat: Dandaharipur
Work Code: OD/346/3298/116051/393819/00107098 (REPAIR AND MAINTENANCE OF THE ROAD AND BRIDGE FROM RD ROAD TO KAMARIPUR PWD ROAD VIA-KRUSHNAPUR HATIPANDA)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Bahanaga Proposal Date: 13-07-2018
Date of Commencement: 24-03-2026 Date of Completion: 04-04-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: Repair and Maintenance
Name of Executant: KISAN KUMAR MURMU
Administrative Approval Details
Approval No.: OD/346/3298/116051/393819/00107098/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3298/116051/393819/00107098/TS
Fund Sanction No.: 9122
Fund Sanction Amount (in Rs.): 450000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Road Work (AR1308) : moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. Cum 58.8706272 2320.4580425996 136606.82035912
2 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. Cum 58.8706272 3186.6069811307 187597.55161906
3 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. Cum 39.023948416 2299.4506886784 89733.645060122
Total Amount (in Rs.): 413938.01703831
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled
462
Qty/Unit (B) Total Qty (A*B)
1 Road Work (AR1308) : moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 58.8706272 Cubic Meter 1.1333922261484 66.723511216961
2 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 58.8706272 Cubic Meter 1.7667844522968 104.01170883392
3 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 39.023948416 Cubic Meter 1.0600706713781 41.368143197173
Total Qty 212.10336324806
Rate Per Man Day 462
Total Amount 97991.753820602
Total Labour Amount (in Rs.): 97991.753820602
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM025 BRM029 BRM041
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1308) :.moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 58.8706272 Cum 0.89578798586572 52.73560056614 0.384 22.6063208448 - -
2 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 58.8706272 Cum 0.3 17.66118816 - - 1 58.8706272
3 Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 39.023948416 Cum 1.28 49.95065397248 - - - -
Total Qty 120.34744269862 22.6063208448 58.8706272
Rate Per Unit 1249.79 894.79 1367.49
Total Amount 150409.03041031 20227.909828719 80504.993989728
Total Material Amount (in Rs.): 251141.93422875
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM025 BRM029 BRM041
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1308) :.moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 58.8706272 Cum 0.89578798586572 52.73560056614 0.384 22.6063208448 - -
2 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 58.8706272 Cum 0.3 17.66118816 - - 1 58.8706272
3 Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 39.023948416 Cum 1.28 49.95065397248 - - - -
Total Qty 120.34744269862 22.6063208448 58.8706272
Rate Per Unit 146.25 442.25 552.5
Total Amount 17600.813494673 9997.6453936128 32526.021528
Total Royalty Amount (in Rs.): 60124.480416286
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 4500 Rs. 4500
2 Display Citizen Board @ Rs. 1500 Rs. 1500
3 Any Other Lumpsum @ Rs. 30061 Rs. 30061
Total Addition Component Amount (in Rs.): 36061
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 449999.01703831