| State: Odisha |
District: Puri |
Block: Gop |
Gram Panchayat: Gadabhingura |
Work Code: OD/369/3539/120940/409821/00076151 (REPAIR AND RENOVATION OF ROAD FROM KADAMBA Pokhari TO HIGH SCHOOL)
Project Category: Road
| Financial Year: 2025-26 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Gop |
Proposal Date: 30-12-2025 |
| Date of Commencement: 20-01-2026 |
Date of Completion: - |
| Scheme Name: Bikashita Gaon Bikashita Odisha |
Scheme Component Name: Viksit Gaon Vikshit Odisha (VGVO) |
| Project Sub-Category: CC Road |
Project Type: Renovation or Rejuvenation |
| Name of Executant: LOJISMITA MOHAPATRO |
|
Administrative Approval Details
Approval No.: OD/369/3539/120940/409821/00076151/AS
Technical Sanction Details
Technical Sanction No.: OD/369/3539/120940/409821/00076151/TS
Fund Sanction No.: 360000
Fund Sanction Amount (in Rs.): 360000
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
Sqm |
34.684 |
216.23489289764 |
7499.8910252617 |
| 2 |
Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
Cum |
43.9566 |
7823.61900228 |
343899.69103562 |
Total Amount (in Rs.): 351399.58206088
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Semi-Skilled
|
Skilled
|
Un-Skilled
|
| 512 |
562 |
462 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
34.684 |
Square Meter |
- |
- |
0.05 |
1.7342 |
0.05 |
1.7342 |
| 2 |
Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
43.9566 |
Cubic Meter |
4.6 |
202.20036 |
- |
- |
0.68 |
29.890488 |
| Total Qty |
1.7342 |
31.624688 |
202.20036 |
| Rate Per Man Day |
512 |
562 |
462 |
| Total Amount |
887.9104 |
17773.074656 |
93416.56632 |
Total Labour Amount (in Rs.): 112077.551376
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM104 |
BRM092 |
BRM340 |
BRM028 |
BRM056 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
34.684 |
Sqm |
0.00267 |
0.09260628 |
0.126 |
4.370184 |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
43.9566 |
Cum |
- |
- |
- |
- |
3.23 |
141.979818 |
0.45 |
19.78047 |
0.9 |
39.56094 |
| Total Qty |
0.09260628 |
4.370184 |
141.979818 |
19.78047 |
39.56094 |
| Rate Per Unit |
58573.086 |
229.106 |
601.352 |
780.67 |
2556.62 |
| Total Amount |
5424.2356025801 |
1001.235375504 |
85379.847513936 |
15442.0195149 |
101142.2904228 |
Total Material Amount (in Rs.): 208389.62842972
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM104 |
BRM092 |
BRM340 |
BRM028 |
BRM056 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
34.684 |
Sqm |
0.00267 |
0.09260628 |
0.000614 |
0.021295976 |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
43.9566 |
Cum |
- |
- |
- |
- |
3.23 |
141.979818 |
0.45 |
19.78047 |
0.9 |
39.56094 |
| Total Qty |
0.09260628 |
0.021295976 |
141.979818 |
19.78047 |
39.56094 |
| Rate Per Unit |
0 |
0 |
0 |
75.25 |
309.5 |
| Total Amount |
0 |
0 |
0 |
1488.4803675 |
12244.11093 |
Total Royalty Amount (in Rs.): 13732.5912975
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Provision for Contingency @
Rs. 3600
|
Rs. 3600 |
| 2 |
Display Citizen Board @
Rs. 5000
|
Rs. 5000 |
| 3 |
Any Other Lumpsum @
Rs. 0.41
|
Rs. 0.41 |
Total Addition Component Amount (in Rs.): 8600.41
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 359999.99206088