Construction of CC road work at Beheraguda Bhatra Sahi to RD road
OD/366/3517/120486/427957/00071437
SFC Devolution of Fund
5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD
Road
CC Road
6821
13-11-2025
Download
dfgdsfdsfs

Nabarangpur
Nabarangpur
Agnipur

Stage wise Geo-tag Photo:

Before
Status Image
  • Latitude: 19.2222417
  • Longitude: 82.52057
  • Date & Time: 17 Jan 2026, 05:13 PM
Transparency Board
Status Image
  • Latitude: 19.2222367
  • Longitude: 82.5205583
  • Date & Time: 17 Jan 2026, 05:13 PM
During
Status Image
  • Latitude: 19.222505
  • Longitude: 82.52026
  • Date & Time: 17 Jan 2026, 05:13 PM
Completed
Status Image
  • Latitude: 19.222305
  • Longitude: 82.5207167
  • Date & Time: 17 Jan 2026, 05:13 PM

460000
459999.00
1
Download

Stage Officer Date Started Date Completed Status
Case Record Opened SUNIL KHORA (BDO) 20-12-2025 20-12-2025 Approved
Estimate Preparation SUNIL KHORA (BDO) 20-12-2025 08-01-2026 Approved
Technical Sanction ASHISH KUMAR PRADHAN (AEE) 08-01-2026 08-01-2026 Approved
Administrative Approval SUNIL KHORA (BDO) 08-01-2026 12-01-2026 Approved
Work Order Issued SUNIL KHORA (BDO) 12-01-2026 12-01-2026 Generated
Execution In Progress ARABINDA BEHERA (AE / JE) 12-01-2026 17-01-2026 Approved

# Name Action
1 Cover Page View Download
2 Sanction File View Download
3 Ordersheet View Download
4 Location Map View Download
5 Drawing View Download
6 Work site photo View Download
7 Quarry Document View Download
8 Estimate Cover Page View Download
9 Detail Estimate View Download
10 Abstract Estimate View Download
11 Estimation DPR View Download
12 Lead Statement View Download
13 Analysis View Download
14 Technical Sanction View Download
15 Administrative Approval View Download
16 Work Order View Download
1st & Final Bill
17 Attac (BRM340) View Download
18 Attac (BRM044) View Download
19 Geo Tagging View Download
20 Merged Bill Measurement View Download
21 Completion Document View Download