State: Odisha District: Nuapada Block: Khariar Gram Panchayat: Ranimunda
Work Code: OD/368/3532/120795/422055/00052161 (Improvement of Palma Mahabandh Tank)
Project Category: Water Body
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Khariar Proposal Date: -
Date of Commencement: - Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Tank Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 4151
Fund Sanction Amount (in Rs.): 400000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0122Bii) : Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. Cum 1080 361.33930892 390246.4536336
Total Amount (in Rs.): 390246.4536336
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled
462
Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0122Bii) : Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. 1080 Cubic Meter 0.43 464.4
Total Qty 464.4
Rate Per Man Day 462
Total Amount 214552.8
Total Labour Amount (in Rs.): 214552.8
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRMM402 BRMM401
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0122Bii) :.Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. 1080 Cum -0.6666 -719.928 1 1080
Total Qty -719.928 1080
Rate Per Unit 175.38 276.01
Total Amount -126260.97264 298090.8
Total Material Amount (in Rs.): 171829.82736
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit
No data to display.
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 5000 Rs. 5000
2 Provision for Contingency @ Rs. 4000 Rs. 4000
Total Addition Component Amount (in Rs.): 9000
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 399246.4536336