State: Odisha District: Sambalpur Block: Rairakhol Gram Panchayat: Kadaligarh
Work Code: OD/371/3565/121404/382483/00038127 (Repair & maintenance of Tantagard UP School )
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Rairakhol Proposal Date: -
Date of Commencement: 25-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Primary School Building
Project Sub-Category: Elementary School Project Type: Repair and Maintenance
Name of Executant: Manas Ranjan Tripathy
Administrative Approval Details
Approval No.: OD/371/3565/121404/382483/00038127/AS
Technical Sanction Details
Technical Sanction No.: OD/371/3565/121404/382483/00038127/TS
Fund Sanction No.: 27871
Fund Sanction Amount (in Rs.): 200000
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM253 BRM252 BRM142 BRM255 BRM029 BRM340 BRM028 BRM044 BRM006 BRM141 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 258.3 Sqm 0.084 21.6972 - - - - - - - - - - - - - - - - - - - -
2 Painting(AR0901ci) :.Priming one coat with outer surface primer of approved quality oil-bound primer over plastering surfaces(Outer surface) - Priming one coat with outer surface primer of approved quality oil-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 356.115 Sqm - - 0.084 29.91366 - - - - - - - - - - - - - - - - - -
3 Painting(AR0922) :.Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 258.3 Sqm - - - - 0.25 64.575 - - - - - - - - - - - - - - - -
4 Painting(AR0918g) :.Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work .(Outside) - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 356.11 Sqm - - 0.084 29.91324 - - 0.125 44.51375 - - - - - - - - - - - - - -
5 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.0375 Cum - - - - - - - - - - - - - - - - - - - - - -
6 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 0.3375 Cum - - - - - - - - 1 0.3375 - - - - - - - - - - - -
7 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 2.5319 Cum - - - - - - - - - - 2.29 5.798051 0.48 1.215312 0.96 2.430624 - - - - - -
8 Masonry Brick Work (AR0603c) :.Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 2.2425 Cum - - - - - - - - - - 0.672 1.50696 0.28 0.6279 - - 400 897 - - - -
9 Masonry Brick Work (AR0603ci) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 4.14 Cum - - - - - - - - - - 0.672 2.78208 0.28 1.1592 - - 400 1656 - - - -
10 Plastering (AR1014i) :.16mm thick cement Plaster in CM (1:6) over brick work in outside (outside) - 16mm thick cement Plaster in CM (1:6) over brick work in outside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 36 Sqm - - - - - - - - - - 0.043 1.548 0.018 0.648 - - - - - - - -
11 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 32.749 Sqm - - - - - - - - - - - - - - - - - - - - - -
12 Painting(AR0903i) :.Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 31.32 Sqm - - - - - - - - - - - - - - - - - - 0.125 3.915 - -
13 Flooring (AR0802ik) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG crusher broken chips(For repair and maintenance). - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG crusher broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge(For repair and maintenance) . 32.749 Sqm - - - - - - - - - - 0.0858 2.8098642 0.012 0.392988 - - - - - - 0.023 0.753227
Total Qty 21.6972 59.8269 64.575 44.51375 0.3375 14.4449552 4.0434 2.430624 2553 3.915 0.753227
Rate Per Unit 0 0 0 0 69 0 69 189 0 0 189
Total Amount 0 0 0 0 23.2875 0 278.9946 459.387936 0 0 142.359903
Total Royalty Amount (in Rs.): 904.029939