State: Odisha District: Cuttack Block: Mahanga Gram Panchayat: Kurujanga
Work Code: OD/350/3339/117003/399512/00023325 (Improv. Of CC road from Kusunpur Pmgsy Road To Smasan Road)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Mahanga Proposal Date: -
Date of Commencement: 27-11-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: Sushree Rashmita Singh
Administrative Approval Details
Approval No.: OD/350/3339/117003/399512/00023325/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3339/117003/399512/00023325/TS
Fund Sanction No.: 1473
Fund Sanction Amount (in Rs.): 150000
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.760888 Cum - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.8898944 Cum 1 5.8898944 - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.963848 Cum - - 2.29 27.39721192 0.48 5.74264704 0.96 11.48529408 - -
4 Concrete (AR0307) :.First floor - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.20296 Cum - - 3.23 29.7255608 0.45 4.141332 - - 0.9 8.282664
Total Qty 5.8898944 57.12277272 9.88397904 11.48529408 8.282664
Rate Per Unit 81.25 0 335.25 190.5 444.5
Total Amount 478.55392 0 3313.60397316 2187.94852224 3681.644148
Total Royalty Amount (in Rs.): 9661.7505634