State: Odisha District: Sundargarh Block: Sundargarh Gram Panchayat: Kirei
Work Code: OD/373/3588/121761/383907/00041906 (Maintenance of Kirei Market Complex)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Sundargarh Proposal Date: -
Date of Commencement: 09-01-2026 Date of Completion: 07-02-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Market Complex Project Type: New Work
Name of Executant: Puspanjali Bilung
Administrative Approval Details
Approval No.: OD/373/3588/121761/383907/00041906/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3588/121761/383907/00041906/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 450000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM056 BRM341 BRM255 BRM252 BRM141
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.980125 Cum 3.23 38.69580375 0.45 5.39105625 0.9 10.7821125 - - - - - - - -
2 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 1.0935 Cum - - - - - - - - - - - - - -
3 Iron Work(AR1703) :.Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 16.5 Qntl - - - - - - 1 16.5 - - - - - -
4 Roofing (AR1132a) :.Labour for fixing G.C.I. Sheet in roof - Labour for fixing G.C.I. Sheet in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. excluding cost of fitting and as per direction of Engineer-in charge. 144 Sqm - - - - - - - - - - - - - -
5 Painting(AR0918gk) :.Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work(Outside)(For repair and maintenance) . - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge(Outside)(For repair and maintenance). 76.92 Sqm - - - - - - - - 0.125 9.615 0.084 6.46128 - -
6 Painting(AR0903ik) :.Painting two coats of enamel paint in outer surface paint (outer surface)(For repair and maintenance) . - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside)(For repair and maintenance). 53.76 Sqm - - - - - - - - - - - - 0.125 6.72
Total Qty 38.69580375 5.39105625 10.7821125 16.5 9.615 6.46128 6.72
Rate Per Unit 555.297 352.89 2304.53 6218.857 195.21622 125.92622 205.58787
Total Amount 21487.663734964 1902.4498400625 24847.701719625 102611.1405 1877.0039553 813.6445667616 1381.5504864
Total Material Amount (in Rs.): 154921.15480311