State: Odisha District: Mayurbhanj Block: Thakurmunda Gram Panchayat: Talapada
Work Code: OD/365/3510/120396/389021/00049433 (Construction of C.C.Road at Behera Sahi to Pradhan Sahi Khadipal)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Thakurmunda Proposal Date: -
Date of Commencement: 06-04-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: SUBRAT KUMAR NATH
Administrative Approval Details
Approval No.: OD/365/3510/120396/389021/00049433/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3510/120396/389021/00049433/TS
Fund Sanction No.: 35917
Fund Sanction Amount (in Rs.): 447576
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.9775 Cum - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 30.9775 Cum 1 30.9775 - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 36.9775 Cum - - 2.29 84.678475 0.48 17.7492 0.96 35.4984 - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 23.233125 Cum - - 3.23 75.04299375 0.45 10.45490625 - - 0.9 20.9098125
Total Qty 30.9775 159.72146875 28.20410625 35.4984 20.9098125
Rate Per Unit 466.64 644.677 1020.76 1388.87 2442.53
Total Amount 14455.3406 102968.75730934 28789.62349575 49302.662808 51072.844325625
Total Material Amount (in Rs.): 246589.22853872