State: Odisha District: Angul Block: Kaniha Gram Panchayat: Bijigol
Work Code: OD/344/3280/115670/403845/00017496 (Const. of CC Road from Bipin Sahoo House to Ambabana Bandha at Rangabeda)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Kaniha Proposal Date: 31-12-2024
Date of Commencement: 25-07-2025 Date of Completion: 13-03-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: Jitendra Naik
Administrative Approval Details
Approval No.: OD/344/3280/115670/403845/00017496/AS
Technical Sanction Details
Technical Sanction No.: OD/344/3280/115670/403845/00017496/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 359740
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 7.2 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 26.28 Cum 1 26.28 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 26.28 Cum - - 2.29 60.1812 0.48 12.6144 0.96 25.2288 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 26.28 Cum - - 3.23 84.8844 0.45 11.826 - - 0.9 23.652 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 86.4 Sqm - - - - - - - - - - 0.00267 0.230688 0.126 10.8864
Total Qty 26.28 145.0656 24.4404 25.2288 23.652 0.230688 10.8864
Rate Per Unit 413.05 538.472 417.99 1401.46 1802.83 58620.646 276.666
Total Amount 10854.954 78113.7637632 10215.842796 35357.154048 42640.53516 13523.079584448 3011.8967424
Total Material Amount (in Rs.): 193717.22609405