State: Odisha District: Malkangiri Block: Mathili Gram Panchayat: Chedenga
Work Code: OD/364/3485/120011/430403/00038438 (Repair & Maintainance of Primary School Sanakarapally )
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Mathili Proposal Date: -
Date of Commencement: 12-01-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Primary School Building
Project Sub-Category: Elementary School Project Type: Repair and Maintenance
Name of Executant: Divyasingh Brahma
Administrative Approval Details
Approval No.: OD/364/3485/120011/430403/00038438/AS
Technical Sanction Details
Technical Sanction No.: OD/364/3485/120011/430403/00038438/TS
Fund Sanction No.: 27871
Fund Sanction Amount (in Rs.): 300000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRMMR0025 BRM002 BRM340 BRM028 BRM341 BRM044 BRM056 BRM140 BRM253 BRM137 BRM141 BRM149 BRM031
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1624) :.Dismantling and removing R.C.C. columns beams slab staircase landing lintels - Dismantling and removing R.C.C. columns beams slab staircase landing lintels including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 7.16625 Cum - - - - - - - - - - - - - - - - - - - - - - - - - -
2 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 51.3595 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
3 Dismantling (AR1613) :.Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 215.8582 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
4 Masonry Brick Work (AR0603ei) :.C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 5.31254 Cum 1 5.31254 400 2125.016 0.672 3.57002688 0.28 1.4875112 - - - - - - - - - - - - - - - - - -
5 Iron Work(AR1703) :.Iron work wrought and put up in trusses and record racks - Iron work wrought and put up in trusses and record racks including all cost of labour, material, machinery and T & P required for the work etc. as per direction of Engineer-in-Charge. 1.716 Qntl - - - - - - - - 1 1.716 - - - - - - - - - - - - - - - -
6 Roofing (AR1132a) :.Labour for fixing G.C.I. Sheet in roof - Labour for fixing G.C.I. Sheet in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. excluding cost of fitting and as per direction of Engineer-in charge. 76.72 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
7 Concrete (AR0304) :.Cement concrete (1:4:8) with 4 cm. hard granite(Crusher Broken) metal - Cement concrete (1:4:8) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 5.1893 Cum - - - - 1.72 8.925596 0.48 2.490864 - - 0.96 4.981728 - - - - - - - - - - - - - -
8 Flooring (AR0802i) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG crusher broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG crusher broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 52.6175 Sqm - - - - 0.0858 4.5145815 0.012 0.63141 - - - - 0.023 1.2102025 - - - - - - - - - - - -
9 Plastering (AR1014k) :.16mm thick cement Plaster in CM (1:6) over brick work in inside (inside)(For repair and maintenance) . - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc. comp. and as per direction of Engineer-in-charge(For repair and maintenance). 115.7115 Sqm - - - - 0.043 4.9755945 0.018 2.082807 - - - - - - - - - - - - - - - - - -
10 Plastering (AR1004ik) :.12mm thick cement plaster (1:6) over Brick work in outside(For repair and maintenance). - 12mm thick cement plaster (1:6) over Brick work in outside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc. comp. and as per direction of Engineer-in-charge(For repair and maintenance). 146.22499999214 Sqm - - - - 0.0358 5.2348549997186 0.015 2.1933749998821 - - - - - - - - - - - - - - - - - -
11 Painting(AR0920b) :.Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat waterbound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat waterbound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 155.1215 Sqm - - - - - - - - - - - - - - 0.125 19.3901875 0.084 13.030206 - - - - - - - -
12 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 25.07625 Sqm - - - - - - - - - - - - - - - - - - 0.054 1.3541175 0.125 3.13453125 - - - -
13 Dismantling (AR1616) :.Dismantling G.C.I. or A.C. sheet roofing - Dismantling G.C.I. or A.C. sheet roofing after carefully removing the bolts and nuts including stacking of he materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 29.0628 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - -
14 Roofing (AR1132) :.Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 29.0628 Sqm - - - - - - - - - - - - - - - - - - - - - - 1 29.0628 - -
15 Plastering (AR1033) :.White washing two coats with stone lime in any surface - White washing two coats with stone lime in any surface including all costs of labour, coaltar and brushes required for the work etc. complete and as per direction of Engineer-in-charge. 78.817 Sqm - - - - - - - - - - - - - - - - - - - - - - - - 1.149247311828 90.580225376344
Total Qty 5.31254 2125.016 27.220653879719 8.8859671998821 1.716 4.981728 1.2102025 19.3901875 13.030206 1.3541175 3.13453125 29.0628 90.580225376344
Rate Per Unit 33 5.15861 573.977 483.09 6214.317 1949.16 2350.53 249.70677 159.39677 143.06677 205.70677 318.453602 21.88
Total Amount 175.31382 10962.12878776 15624.029251919 4292.721894591 10663.767972 9710.18494848 2844.617282325 4841.8610903194 2076.9727488346 193.72921692547 644.79429890156 9255.1533442056 1981.8953312344
Total Material Amount (in Rs.): 73267.169987496