State: Odisha District: Kalahandi Block: Madanpur Rampur Gram Panchayat: Gochhandengaon
Work Code: OD/358/3419/118813/422432/00099664 (Construction of Market Complex at Gochhadengen)
Project Category: Building
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Madanpur Rampur Proposal Date: -
Date of Commencement: - Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Creation of Capital Asset for Revenue Generation
Project Sub-Category: Market Complex Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 9112/PRandDW
Fund Sanction Amount (in Rs.): 1000000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM162 BRM341 BRM340 BRM028 BRM060 BRM052 BRM104 BRM092 BRM084 BRM094 BRM002 BRMMR0025 BRM140 BRM253 BRM255 BRM137 BRM141 BRM045 BRM056 BRM174 BRM131 BRMMR0027
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 64.656 Cum 1 64.656 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 19.8 Qntl - - 0.8 15.84 1.05 20.79 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
3 R.C.C. Work (AR0404Aa) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) 8.1 Cum - - - - - - 3.4733 28.13373 0.45 3.645 0.36 2.916 0.54 4.374 0.004005 0.0324405 0.189 1.5309 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 R.C.C. Work (AR0404Ab) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) 2.4 Cum - - - - - - 3.4733 8.33592 0.45 1.08 0.36 0.864 0.54 1.296 0.01335 0.03204 0.63 1.512 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
5 R.C.C. Work (AR0404Ac) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 3.96 Cum - - - - - - 3.4733 13.754268 0.45 1.782 0.36 1.4256 0.54 2.1384 0.041529 0.16445484 - - 4.4196 17.501616 - - - - - - - - - - - - - - - - - - - - - - - - - -
6 R.C.C. Work (AR0404Ad) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 1.6008 Cum - - - - - - 3.4733 5.56005864 0.45 0.72036 0.36 0.576288 0.54 0.864432 0.0741335 0.1186729068 - - - - 3.7695 6.0342156 - - - - - - - - - - - - - - - - - - - - - - - -
7 R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 6.6 Cum - - - - - - 3.4733 22.92378 0.45 2.97 0.36 2.376 0.54 3.564 0.0502172 0.33143352 - - 6.2216 41.06256 - - - - - - - - - - - - - - - - - - - - - - - - - -
8 Masonry Brick Work (AR0603e) :.C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 18.261 Cum - - - - - - 0.672 12.271392 0.28 5.11308 - - - - - - - - - - - - 400 7304.4 - - - - - - - - - - - - - - - - - - - - - -
9 Masonry Brick Work (AR0603ei) :.C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with C.B. Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 19.4212 Cum - - - - - - 0.672 13.0510464 0.28 5.437936 - - - - - - - - - - - - 400 7768.48 1 19.4212 - - - - - - - - - - - - - - - - - - - -
10 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 7.8091776 Qntl - - - - 1 7.8091776 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
11 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 134.44 Sqm - - - - - - 0.0358 4.812952 0.015 2.0166 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
12 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 101.16 Sqm - - - - - - 0.043 4.34988 0.018 1.82088 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
13 Painting(AR0920b) :.Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat waterbound Primer on new work (Inside) - Finishing wall surface with two coats with plastic emulsion paint of approved shades above one coat waterbound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 133.8 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - 0.125 16.725 0.084 11.2392 - - - - - - - - - - - - - - - -
14 Painting(AR0918h) :.Finishing wall with two coats weather coat paint of approved shade including one coat of water bound primer in the outer surface of old work(Outside). - Finishing wall with two coats weather coat paint of approved shade including one coat of water bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 112.2 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.090322580645161 10.134193548387 0.125 14.025 - - - - - - - - - - - - - -
15 Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 13.23 Sqm - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.054 0.71442 0.125 1.65375 - - - - - - - - - -
16 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 23.112 Cum - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
17 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 9.189 Cum - - - - - - 2.29 21.04281 0.48 4.41072 - - - - - - - - - - - - - - - - - - - - - - - - - - 0.96 8.82144 - - - - - - - -
18 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 1.3125 Cum - - - - - - 3.23 4.239375 0.45 0.590625 - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.9 1.18125 - - - - - -
19 Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 32.64 Sqm - - - - - - 0.1074 3.505536 0.021 0.68544 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0076 0.248064 1 32.64 - -
20 Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 5.94 Sqm - - - - - - 0.1375 0.81675 0.015 0.0891 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 5.94 1 5.94
Total Qty 64.656 15.84 28.5991776 142.79749804 30.361741 8.157888 12.236832 0.6790417668 3.0429 58.564176 6.0342156 15072.88 19.4212 16.725 21.373393548387 14.025 0.71442 1.65375 8.82144 1.18125 0.248064 38.58 5.94
Rate Per Unit 413.05 90.1 6391.452 602.612 417.99 2256.91 2241.91 58573.086 229.106 250.166 240.106 5.15861 33 249.64732 159.33732 189.80732 143.00732 205.64732 1258.67 2258.53 2047.912 665.5902781 8.5
Total Amount 26706.1608 1427.184 182790.27086988 86051.48588888 12690.90412059 18411.61900608 27433.87602912 39773.571804368 697.1466474 14650.765653216 1448.8513708536 77755.1094968 640.8996 4175.351427 3405.5792473053 2662.047663 102.1672895544 340.08925545 11103.2818848 2667.8885625 508.013242368 25678.472929098 50.49
Total Material Amount (in Rs.): 541171.22678826