State: Odisha District: Kandhamal Block: Tikabali Gram Panchayat: Gardingia
Work Code: OD/359/3432/119002/415980/00049190 (IMPROVEMENT OF ROAD AT ABENSORA ABASAHI MANDAGUDA)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Tikabali Proposal Date: -
Date of Commencement: 06-04-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: BHAJARAM BEHERA
Administrative Approval Details
Approval No.: OD/359/3432/119002/415980/00049190/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3432/119002/415980/00049190/TS
Fund Sanction No.: 1990
Fund Sanction Amount (in Rs.): 201457
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.275436537152 Cubic Meter 0.516 1.6901252531704 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 14.18584747424 Cubic Meter 0.1236 1.7533707478161 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 18.276460121088 Cubic Meter 3.9 71.278194472243 - - 0.18 3.2897628217958
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.043552 Cubic Meter 4.6 50.8003392 - - 0.68 7.50961536
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 38.26117152 Square Meter - - 0.05 1.913058576 0.05 1.913058576
Total Qty 125.52202967323 12.712436757796 1.913058576
Rate Per Man Day 462 562 512
Total Amount 57991.177709032 7144.3894578813 979.485990912
Total Labour Amount (in Rs.): 66115.053157825