State: Odisha District: Sundargarh Block: Hemgir Gram Panchayat: Topria
Work Code: OD/373/3578/121608/383497/00040065 (Construction of Culvert at Samarpinda PWD road to Basti road)
Project Category: CD Work
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Hemgir Proposal Date: -
Date of Commencement: 07-02-2026 Date of Completion: 29-03-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: Slab Culvert Project Type: New Work
Name of Executant: Aurobinda Prasad Behura
Administrative Approval Details
Approval No.: OD/373/3578/121608/383497/00040065/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3578/121608/383497/00040065/TS
Fund Sanction No.: 29133
Fund Sanction Amount (in Rs.): 400000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
462 562 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 38.691 Cubic Meter 0.516 19.964556 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.6295 Cubic Meter 0.1236 0.6958062 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 41.841 Cubic Meter 3.9 163.1799 - - 0.18 7.53138 - -
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.68625 Cubic Meter 4.6 3.15675 - - 0.68 0.46665 - -
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 99.12 Square Meter - - 0.05 4.956 0.05 4.956 - -
6 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 24.07 Square Meter - - 0.30555555555556 7.3547222222222 0.30555555555556 7.3547222222222 - -
7 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 4.58 Quintal 0.8 3.664 0.044 0.20152 - - 0.3 1.374
8 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 5.673 Cubic Meter 1.3333 7.5638109 0.0573 0.3250629 0.1 0.5673 - -
Total Qty 198.2248231 20.876052222222 12.837305122222 1.374
Rate Per Man Day 462 562 512 612
Total Amount 91579.8682722 11732.341348889 6572.7002225778 840.888
Total Labour Amount (in Rs.): 110725.79784367