State: Odisha District: Jagatsinghpur Block: Tirtol Gram Panchayat: Birtol
Work Code: OD/355/3393/118210/397631/00058417 (Construction of CC roa from Adil Khan house to Moi Khan house Ward No.-12)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Tirtol Proposal Date: -
Date of Commencement: 09-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: PARTHA SARATHI DASH
Administrative Approval Details
Approval No.: OD/355/3393/118210/397631/00058417/AS
Technical Sanction Details
Technical Sanction No.: OD/355/3393/118210/397631/00058417/TS
Fund Sanction No.: 1990
Fund Sanction Amount (in Rs.): 201457
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
462 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.5375 Cubic Meter 0.1236 1.673235 - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.11 Cubic Meter 3.9 51.129 0.18 2.3598
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.4 Cubic Meter 4.6 52.44 0.68 7.752
4 Earth Work (AR0101a) : Earthwork in ordinary soil within 50m, initial lead and 1.5m, initial lift - Earth work in ordinary soil within 50m, initial lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 3.8475 Cubic Meter 0.32 1.2312 - -
Total Qty 106.473435 10.1118
Rate Per Man Day 462 562
Total Amount 49190.72697 5682.8316
Total Labour Amount (in Rs.): 54873.55857