State: Odisha District: Kandhamal Block: K.Nuagan Gram Panchayat: Bondaguda
Work Code: OD/359/3426/118924/416119/00035797 (Renovation Of Tank At Bondaguda)
Project Category: Water Body
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, K.Nuagan Proposal Date: 20-07-2023
Date of Commencement: 06-04-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Tank Project Type: Renovation or Rejuvenation
Name of Executant: SANDHYARANI PRADHAN
Administrative Approval Details
Approval No.: OD/359/3426/118924/416119/00035797/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3426/118924/416119/00035797/TS
Fund Sanction No.: 15596
Fund Sanction Amount (in Rs.): 600000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
462 562 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 41.5124288 Cubic Meter 0.516 21.4204132608 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.3162272 Cubic Meter 0.1236 1.15148568192 - - - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 9.3162272 Cubic Meter 3.9 36.33328608 - - 0.18 1.676920896 - -
4 R.C.C. Work (AR0403A) : Reinforced cement concrete work of M-15 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-15 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 29.5061056 Cubic Meter 1.33 39.243120448 0.06 1.770366336 0.1 2.95061056 - -
5 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 29.2512544 Cubic Meter 1.3333 39.00069749152 0.0573 1.67609687712 0.1 2.92512544 - -
6 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 15.14 Quintal 0.8 12.112 0.044 0.66616 - - 0.3 4.542
7 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 151.989308 Square Meter - - 0.05 7.5994654 0.05 7.5994654 - -
Total Qty 149.26100296224 15.152122296 11.71208861312 4.542
Rate Per Man Day 462 562 512 612
Total Amount 68958.583368555 8515.492730352 5996.5893699174 2779.704
Total Labour Amount (in Rs.): 86250.369468824