State: Odisha District: Nabarangpur Block: Jhorigam Gram Panchayat: Dhamanaguda
Work Code: OD/366/3515/120451/427614/00056399 (Construction work of VSS building at Dhamanaguda village of Dhamanaguda GP)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Jhorigam Proposal Date: 22-08-2024
Date of Commencement: 16-03-2026 Date of Completion: -
Scheme Name: Construction of Vana Suraksha Samiti Building Scheme Component Name: Construction of Buildings for Vana Suraksha Samiti
Project Sub-Category: Vana Suraksha Samiti Building Project Type: New Work
Name of Executant: Sagram Marndi
Administrative Approval Details
Approval No.: OD/366/3515/120451/427614/00056399/AS
Technical Sanction Details
Technical Sanction No.: OD/366/3515/120451/427614/00056399/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 850000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
462 562 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0122Aia) : Earthwork in all kinds of soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift - Earthwork in all kinds of soil in foundation and plinth within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge 28.2582 Cubic Meter 0.5682408 16.05746217456 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 23.8659 Cubic Meter 0.1236 2.94982524 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 15.774475 Cubic Meter 3.9 61.5204525 - - 0.18 2.8394055 - -
4 R.C.C. Work (AR0404A) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (excluding centring and shuttering) 18.78304945 Cubic Meter 1.3333 25.043439831685 0.0573 1.076268733485 0.1 1.878304945 - -
5 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 19.1 Quintal 0.8 15.28 0.044 0.8404 - - 0.3 5.73
6 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 108.1054 Square Meter - - 0.05 5.40527 0.05 5.40527 - -
7 R.C.C. Work (AR0410e) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm 9.822 Square Meter - - 0.16025641025641 1.5740384615385 0.16025641025641 1.5740384615385 - -
8 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 13.096 Square Meter - - 0.6547619047619 8.5747619047619 0.6547619047619 8.5747619047619 - -
9 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 47.768 Square Meter - - 0.30555555555556 14.595777777778 0.30555555555556 14.595777777778 - -
10 Masonry Brick Work (AR0603ci) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 22.146585 Cubic Meter 2.96 65.5538916 - - 1.05 23.25391425 0.35 7.75130475
11 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 2.7198 Quintal 6.3976377952756 17.400295275591 1.9685039370079 5.353937007874 3.9370078740157 10.707874015748 3.4448818897638 9.3693897637795
12 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 130.0236 Square Meter 0.24 31.205664 - - 0.16 20.803776 - -
13 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 81.385 Square Meter 0.12 9.7662 - - 0.14 11.3939 - -
14 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 81.385 Square Meter 0.11776344086022 9.5841776344086 - - - - 0.10776344086022 8.7703276344086
15 Painting (AR0922a) : Finishing wall surface with two coats with distemper of approved shades above one coat oil bound Primer on new work (Inside) - Finishing wall surface with two coats with distemper of approved shades above one coat oil bound Primer on new work to give an even shade including all costs of labor, Paint, Primer, Brushes and putty required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 130.023 Square Meter 0.11576344086022 15.051909870968 - - - - 0.10576344086022 13.751679870968
16 Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. 27.50625 Square Meter 0.17204301075269 4.7322580645161 - - - - 0.18817204301075 5.1759072580645
17 Flooring (AR0816) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 36.895 Square Meter 0.216 7.96932 0.55 20.29225 - - 0.216 7.96932
18 Flooring (AR0817a) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge 9.2325 Square Meter 0.325 3.0005625 0.76 7.0167 - - 0.325 3.0005625
Total Qty 285.11545869173 101.02702285483 64.729403885437 61.51849177722
Rate Per Man Day 462 562 512 612
Total Amount 131723.34191558 56777.186844412 33141.454789344 37649.316967659
Total Labour Amount (in Rs.): 259291.30051699