State: Odisha District: Nabarangpur Block: Chandahandi Gram Panchayat: Beheramunda
Work Code: OD/366/3513/120420/427459/00040741 (Const of CC Road at Ghane Sahi Belmajhiguda)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Chandahandi Proposal Date: 15-05-2025
Date of Commencement: 19-02-2026 Date of Completion: 13-03-2026
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: Nilakantha Pattnaik
Administrative Approval Details
Approval No.: OD/366/3513/120420/427459/00040741/AS
Technical Sanction Details
Technical Sanction No.: OD/366/3513/120420/427459/00040741/TS
Fund Sanction No.: 15612
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.944 Cubic Meter 0.1236 1.3526784 - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 16.416 Cubic Meter 3.9 64.0224 - - 0.18 2.95488
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 15.2 Square Meter - - 0.05 0.76 0.05 0.76
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 10.944 Cubic Meter 4.6 50.3424 - - 0.68 7.44192
Total Qty 115.7174784 11.1568 0.76
Rate Per Man Day 462 562 512
Total Amount 53461.4750208 6270.1216 389.12
Total Labour Amount (in Rs.): 60120.7166208