State: Odisha District: Jharsuguda Block: Laikera Gram Panchayat: Sahaspur
Work Code: OD/357/3407/118557/381197/00049307 (IMPROVEMENT OF MARKET COMPLEX ,SAHASPUR)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Laikera Proposal Date: -
Date of Commencement: 17-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Market Complex Project Type: Upgradation or Improvement
Name of Executant: Diptee Nayak
Administrative Approval Details
Approval No.: OD/357/3407/118557/381197/00049307/AS
Technical Sanction Details
Technical Sanction No.: OD/357/3407/118557/381197/00049307/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 5.76069 5716.99017714 32933.808143549
2 Plastering (AR1004) : First Floor - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. Sqm 88.985 177.7226424028 15814.649334213
3 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. Sqm 228.731 248.670609038 56878.677075871
4 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. Sqm 77.0215 190.1857568152 14648.392268542
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. Sqm 79.9225 361.5699629028 28897.575360099
6 miscellaneous (ARM105) : Labour for fitting and fixing of M.S. window grills including cost of screws complete. (Iron works) and as directed by Engineer-in-Charge. - Labour for fitting and fixing of M.S. window grills including cost of screws complete. (Iron works) and as directed by Engineer-in-Charge. Sqm 20.58 16.22 333.8076
7 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. Qntl 7.1 15763.084563087 111917.90039792
8 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. Sqm 424.19 71.83753306751 30472.763151907
Total Amount (in Rs.): 291897.5733321
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Highly-Skilled Semi-Skilled
562 462 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 5.76069 Cubic Meter 3.9 22.466691 - - 0.18 1.0369242 - -
2 Plastering (AR1004) : First Floor - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 88.985 Square Meter 0.1236 10.998546 - - 0.1442 12.831637 - -
3 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 228.731 Square Meter 0.24 54.89544 - - 0.16 36.59696 - -
4 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 77.0215 Square Meter 0.17 13.093655 - - 0.14 10.78301 - -
5 Flooring (AR0802ii) : 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 79.9225 Square Meter 0.36 28.7721 - - - - 0.13 10.389925
7 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 7.1 Quintal 6.3976377952756 45.423228346457 1.9685039370079 13.976377952756 3.9370078740157 27.952755905512 3.4448818897638 24.458661417323
8 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 424.19 Square Meter 0.053763440860215 22.805913978495 - - - - 0.053763440860215 22.805913978495
Total Qty 89.201287105512 198.45557432495 57.654500395817 13.976377952756
Rate Per Man Day 562 462 612 512
Total Amount 50131.123353298 91686.475338128 35284.55424224 7155.905511811
Total Labour Amount (in Rs.): 184258.05844548
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM057 BRMM105 BRM341 BRM253
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 5.76069 Cum 2.29 13.1919801 0.48 2.7651312 0.96 5.5302624 - - - - - - - -
2 Plastering (AR1004) :.First Floor - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 88.985 Sqm 0.0358 3.185663 0.015 1.334775 - - - - - - - - - -
3 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 228.731 Sqm 0.043 9.835433 0.018 4.117158 - - - - - - - - - -
4 Plastering (AR1027) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 77.0215 Sqm 0.0372 2.8651998 0.0075 0.57766125 - - - - - - - - - -
5 Flooring (AR0802ii) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 79.9225 Sqm 0.0858 6.8573505 0.012 0.95907 - - 0.023 1.8382175 - - - - - -
6 miscellaneous(ARM105) :.Labour for fitting and fixing of M.S. window grills including cost of screws complete. (Iron works) and as directed by Engineer-in-Charge. - Labour for fitting and fixing of M.S. window grills including cost of screws complete. (Iron works) and as directed by Engineer-in-Charge. 20.58 Sqm - - - - - - - - 1 20.58 - - - -
7 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 7.1 Qntl - - - - - - - - - - 1 7.1 - -
8 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 424.19 Sqm - - - - - - - - - - - - 0.084 35.63196
Total Qty 35.9356264 9.75379545 5.5302624 1.8382175 20.58 7.1 35.63196
Rate Per Unit 539.202 805.71 1726.96 1816.9 16.22 6210.252 159.33732
Total Amount 19376.561626133 7858.7305320195 9550.541954304 3339.85737575 333.8076 44092.7892 5677.5010127472
Total Material Amount (in Rs.): 90229.789300954
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM057 BRM341 BRM253
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 5.76069 Cum 2.29 13.1919801 0.48 2.7651312 0.96 5.5302624 - - - - - -
2 Plastering (AR1004) :.First Floor - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 88.985 Sqm 0.0358 3.185663 0.015 1.334775 - - - - - - - -
3 Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 228.731 Sqm 0.043 9.835433 0.018 4.117158 - - - - - - - -
4 Plastering (AR1027) :.6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 77.0215 Sqm 0.0372 2.8651998 0.0075 0.57766125 - - - - - - - -
5 Flooring (AR0802ii) :.2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips - 2.5 cm thick A.S. flooring in C.C (1:2:4) with 12 mm size HG Hand broken chips including punning incl. cost, conveyance & royalty of materials as per direction of Engineer-in-charge. 79.9225 Sqm 0.0858 6.8573505 0.012 0.95907 - - 0.023 1.8382175 - - - -
6 miscellaneous(ARM105) :.Labour for fitting and fixing of M.S. window grills including cost of screws complete. (Iron works) and as directed by Engineer-in-Charge. - Labour for fitting and fixing of M.S. window grills including cost of screws complete. (Iron works) and as directed by Engineer-in-Charge. 20.58 Sqm - - - - - - - - - - - -
7 Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 7.1 Qntl - - - - - - - - 1 7.1 - -
8 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 424.19 Sqm - - - - - - - - - - 0.084 35.63196
Total Qty 35.9356264 9.75379545 5.5302624 1.8382175 7.1 35.63196
Rate Per Unit 0 210.25 174.5 174.5 0 0
Total Amount 0 2050.7354933625 965.0307888 320.76895375 0 0
Total Royalty Amount (in Rs.): 3336.5352359125
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ 1% Rs. 2918.975733321
2 Display Citizen Board @ Rs. 5183 Rs. 5183
Total Addition Component Amount (in Rs.): 8101.975733321
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 299999.54906542