State: Odisha District: Mayurbhanj Block: Bahalda Gram Panchayat: Asana
Work Code: OD/365/3488/120068/387540/00047683 (Renovation of Tolabandha at Jialda)
Project Category: Water Body
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Bahalda Proposal Date: -
Date of Commencement: 21-02-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Tank Project Type: Renovation or Rejuvenation
Name of Executant: SARANGADHAR PRADHAN
Administrative Approval Details
Approval No.: OD/365/3488/120068/387540/00047683/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3488/120068/387540/00047683/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 400000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0116) : Fine dressing and turfing with initial lead of 50m and 1.5m initial lift - Fine dressing and turfing with initial lead of 50m and 1.5m initial lift as per direction of Engineer-in-charge Sqm 1440 13.718628 19754.82432
2 Special items for irrigation works (AR0216) : Excavation, loading, unloading, and carriage by mechanical means of all kinds of soil, including stoney earth, gravel, and moorum etc interspread with boulders upto 1/2 cum within an initial lead of 1km from the place of excavation. - Excavation, loading, unloading, and carriage by mechanical means of all kinds of soil, including stoney earth, gravel, and moorum etc interspread with boulders upto 1/2 cum size with all lifts and delifts including trimming of slopes and bed to design section and depositing the the excavated materials away from work site as per the specification and as directed by the Engineer-in-charge within an initial lead of 1km from the place of excavation complete. Per 1 cum. Cum 5125 67.165 344220.625
3 Site Clearance (AR1403i) : Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials - Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness and as per direction of Engineer-in-Charge (in area of light jungle) Sqm 960 7.34568455 7051.857168
Total Amount (in Rs.): 371027.306488
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled
462 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0116) : Fine dressing and turfing with initial lead of 50m and 1.5m initial lift - Fine dressing and turfing with initial lead of 50m and 1.5m initial lift as per direction of Engineer-in-charge 1440 Square Meter 0.0294 42.336 - -
3 Site Clearance (AR1403i) : Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials - Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness and as per direction of Engineer-in-Charge (in area of light jungle) 960 Square Meter 0.015 14.4 0.0006 0.576
Total Qty 56.736 0.576
Rate Per Man Day 462 512
Total Amount 26212.032 294.912
Total Labour Amount (in Rs.): 26506.944
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRMMR0065 BRMMR0102 BRMMR0104
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0116) :.Fine dressing and turfing with initial lead of 50m and 1.5m initial lift - Fine dressing and turfing with initial lead of 50m and 1.5m initial lift as per direction of Engineer-in-charge 1440 Sqm - - - - - -
2 Special items for irrigation works(AR0216) :.Excavation, loading, unloading, and carriage by mechanical means of all kinds of soil, including stoney earth, gravel, and moorum etc interspread with boulders upto 1/2 cum within an initial lead of 1km from the place of excavation. - Excavation, loading, unloading, and carriage by mechanical means of all kinds of soil, including stoney earth, gravel, and moorum etc interspread with boulders upto 1/2 cum size with all lifts and delifts including trimming of slopes and bed to design section and depositing the the excavated materials away from work site as per the specification and as directed by the Engineer-in-charge within an initial lead of 1km from the place of excavation complete. Per 1 cum. 5125 Cum 1 5125 1 5125 1 5125
3 Site Clearance (AR1403i) :.Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials - Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness and as per direction of Engineer-in-Charge (in area of light jungle) 960 Sqm - - - - - -
Total Qty 5125 5125 5125
Rate Per Unit 1 25.01 40.49
Total Amount 5125 128176.25 207511.25
Total Material Amount (in Rs.): 340812.5
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit
No data to display.
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Display Citizen Board @ Rs. 5000 Rs. 5000
2 Any Other Lumpsum @ Rs. 19972.5 Rs. 19972.5
3 Provision for Contingency @ Rs. 4000 Rs. 4000
Total Addition Component Amount (in Rs.): 28972.5
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 399999.806488