State: Odisha District: Nayagarh Block: Bhapur Gram Panchayat: Bijipur
Work Code: OD/367/3523/120594/406113/00089141 (Development of Sukapokhari to Baramana road)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Bhapur Proposal Date: -
Date of Commencement: 20-02-2026 Date of Completion: 09-03-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: Aishwarya Rajalaxmi Nath
Administrative Approval Details
Approval No.: OD/367/3523/120594/406113/00089141/AS
Technical Sanction Details
Technical Sanction No.: OD/367/3523/120594/406113/00089141/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 500000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 39 216.23489289764 8433.160823008
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 71.175 6781.21878808 482653.24724159
Total Amount (in Rs.): 491086.4080646
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Semi-Skilled Skilled Un-Skilled
512 562 462
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 39 Square Meter - - 0.05 1.95 0.05 1.95
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 71.175 Cubic Meter 4.6 327.405 - - 0.68 48.399
Total Qty 1.95 50.349 327.405
Rate Per Man Day 512 562 462
Total Amount 998.4 28296.138 151261.11
Total Labour Amount (in Rs.): 180555.648
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM104 BRM092 BRM340 BRM028 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 39 Sqm 0.00267 0.10413 0.126 4.914 - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 71.175 Cum - - - - 3.23 229.89525 0.45 32.02875 0.9 64.0575
Total Qty 0.10413 4.914 229.89525 32.02875 64.0575
Rate Per Unit 58573.086 229.106 547.857 430.15 1802.83
Total Amount 6099.21544518 1125.826884 125949.72197925 13777.1668125 115484.782725
Total Material Amount (in Rs.): 262436.71384593
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM104 BRM092 BRM340 BRM028 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 39 Sqm 0.00267 0.10413 0.000614 0.023946 - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 71.175 Cum - - - - 3.23 229.89525 0.45 32.02875 0.9 64.0575
Total Qty 0.10413 0.023946 229.89525 32.02875 64.0575
Rate Per Unit 0 0 0 305.25 199.5
Total Amount 0 0 0 9776.7759375 12779.47125
Total Royalty Amount (in Rs.): 22556.2471875
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 5000 Rs. 5000
2 Display Citizen Board @ Rs. 1500 Rs. 1500
3 Any Other Lumpsum @ Rs. 2400 Rs. 2400
Total Addition Component Amount (in Rs.): 8900
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 499986.4080646