State: Odisha District: Ganjam Block: Bellaguntha Gram Panchayat: Mangalpur
Work Code: OD/354/3366/117627/410705/00058645 (Construction of PWD Road to Nabarantapur Village)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Bellaguntha Proposal Date: -
Date of Commencement: - Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: Pavor Block Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 3004
Fund Sanction Amount (in Rs.): 201457
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 6.1482852 240.77592 1480.3590254524
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 18.03496992 683.086432 12319.44325388
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 71.721116 216.39264180804 15519.921764661
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 8.1977136 6914.9609499 56686.869422464
5 miscellaneous (ARM287) : Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. Sqm 152.4073715 626.9766 95555.855598007
Total Amount (in Rs.): 181562.44906446
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled Skilled
462 512 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.1482852 Cubic Meter 0.516 3.1725151632 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.03496992 Cubic Meter 0.1236 2.229122282112 - - - -
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 71.721116 Square Meter - - 0.05 3.5860558 0.05 3.5860558
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.1977136 Cubic Meter 4.6 37.70948256 - - 0.68 5.574445248
Total Qty 43.111120005312 3.5860558 9.160501048
Rate Per Man Day 462 512 562
Total Amount 19917.337442454 1836.0605696 5148.201588976
Total Labour Amount (in Rs.): 26901.59960103
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM104 BRM092 BRM340 BRM028 BRM056 BRMM287
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.1482852 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.03496992 Cum 1 18.03496992 - - - - - - - - - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 71.721116 Sqm - - 0.00267 0.19149537972 0.126 9.036860616 - - - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.1977136 Cum - - - - - - 3.23 26.478614928 0.45 3.68897112 0.9 7.37794224 - -
5 miscellaneous(ARM287) :.Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. 152.4073715 Sqm 0.03 4.572221145 - - - - - - - - - - 1 152.4073715
Total Qty 22.607191065 0.19149537972 9.036860616 26.478614928 3.68897112 7.37794224 152.4073715
Rate Per Unit 403.97 58620.646 276.666 591.182 407.34 1737.73 608.4
Total Amount 9132.6269745281 11225.582865202 2500.1920791863 15653.680530365 1502.6654960208 12820.871568715 92724.6448206
Total Material Amount (in Rs.): 145560.26433462
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM104 BRM092 BRM340 BRM028 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.1482852 Cum - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 18.03496992 Cum 1 18.03496992 - - - - - - - - - -
3 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 71.721116 Sqm - - 0.00267 0.19149537972 0.000614 0.044036765224 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.1977136 Cum - - - - - - 3.23 26.478614928 0.45 3.68897112 0.9 7.37794224
5 miscellaneous(ARM287) :.Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. 152.4073715 Sqm 0.03 4.572221145 - - - - - - - - - -
Total Qty 22.607191065 0.19149537972 0.044036765224 26.478614928 3.68897112 7.37794224
Rate Per Unit 215.25 0 0 0 215.25 288.5
Total Amount 4866.1978767413 0 0 0 794.05103358 2128.53633624
Total Royalty Amount (in Rs.): 7788.7852465613
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 2014 Rs. 2014
2 Display Citizen Board @ Rs. 1190 Rs. 1190
3 Any Other Lumpsum @ Rs. 16690 Rs. 16690
Total Addition Component Amount (in Rs.): 19894
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 201456.44906446