State: Odisha District: Mayurbhanj Block: Khunta Gram Panchayat: Sapanchua
Work Code: OD/365/3499/120243/390794/00094804 (Connectivity of Road with Grade-II Metalling and Construction of Culvert from Sapanchua Madan House to Chaudhray Sahi)
Project Category: Road
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Khunta Proposal Date: -
Date of Commencement: 27-03-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: Mettalling Road Project Type: New Work
Name of Executant: Chandan Kumar Gartia
Administrative Approval Details
Approval No.: OD/365/3499/120243/390794/00094804/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3499/120243/390794/00094804/TS
Fund Sanction No.: 1048
Fund Sanction Amount (in Rs.): 500000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. Cum 153.2625 1200.0535686784 183923.21006957
2 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. Cum 100.5 3084.7989811307 310022.29760364
Total Amount (in Rs.): 493945.50767321
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled
462
Qty/Unit (B) Total Qty (A*B)
1 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 153.2625 Cubic Meter 1.0600706713781 162.46908127208
2 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 100.5 Cubic Meter 1.7667844522968 177.56183745583
Total Qty 340.03091872792
Rate Per Man Day 462
Total Amount 157094.2844523
Total Labour Amount (in Rs.): 157094.2844523
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM025 BRM041
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 153.2625 Cum 1.28 196.176 - -
2 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 100.5 Cum 0.3 30.15 1 100.5
Total Qty 226.326 100.5
Rate Per Unit 405.39 1494.81
Total Amount 91750.29714 150228.405
Total Material Amount (in Rs.): 241978.70214
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM025 BRM041
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 153.2625 Cum 1.28 196.176 - -
2 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 100.5 Cum 0.3 30.15 1 100.5
Total Qty 226.326 100.5
Rate Per Unit 140.25 579.5
Total Amount 31742.2215 58239.75
Total Royalty Amount (in Rs.): 89981.9715
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ 1% Rs. 4939.4550767321
2 Display Citizen Board @ Rs. 1115 Rs. 1115
Total Addition Component Amount (in Rs.): 6054.4550767321
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 499999.96274994