| State: Odisha |
District: Balangir |
Block: Titlagarh |
Gram Panchayat: Kholan |
Work Code: OD/345/3296/116013/421550/00037355 (Repair and Maintenance of Kalyan Mandap at Kholan)
Project Category: Building
| Financial Year: 2025-26 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Titlagarh |
Proposal Date: - |
| Date of Commencement: 18-02-2026 |
Date of Completion: - |
| Scheme Name: 5th SFC Grant in Aid |
Scheme Component Name: Maintenance of Capital Assets |
| Project Sub-Category: Kalyan Mandap |
Project Type: Repair and Maintenance |
| Name of Executant: SUNIL KU BAG |
|
Administrative Approval Details
Approval No.: OD/345/3296/116013/421550/00037355/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3296/116013/421550/00037355/TS
Fund Sanction No.: 33742
Fund Sanction Amount (in Rs.): 500000
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only)
|
Sqm |
138 |
1002.2764571386 |
138314.15108513 |
| 2 |
Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles.
|
Sqm |
9.63 |
1520.997839651 |
14647.209195839 |
| 3 |
Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge.
|
Sqm |
432.04 |
79.21834 |
34225.4916136 |
| 4 |
Painting (AR0920) : Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside)
|
Sqm |
469.34 |
94.76013415 |
44474.721361961 |
| 5 |
Flooring (AR0816) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge.
|
Sqm |
6.24 |
1175.7527830438 |
7336.6973661933 |
| 6 |
Flooring (AR0817b) : Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge.
|
Sqm |
20.1 |
871.062839651 |
17508.363076985 |
| 7 |
Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.
|
Sqm |
53.04625 |
230.35420628603 |
12219.4268152 |
| 8 |
Painting (AR0918g) : Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work .(Outside) - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside)
|
Sqm |
272.015 |
156.86604451751 |
42669.91709943 |
| 9 |
Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge.
|
Qntl |
1.2 |
15758.174347087 |
18909.809216504 |
| 10 |
Painting (AR0901c) : Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge.
|
Sqm |
433.705 |
68.99284786751 |
29922.543084378 |
Total Amount (in Rs.): 360228.32991522
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Un-Skilled
|
Highly-Skilled
|
Semi-Skilled
|
Skilled
|
| 462 |
612 |
512 |
562 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only)
|
138 |
Square Meter |
0.216 |
29.808 |
- |
- |
- |
- |
0.216 |
29.808 |
| 2 |
Flooring (AR0817aa) : Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles.
|
9.63 |
Square Meter |
0.325 |
3.12975 |
0.76 |
7.3188 |
- |
- |
0.325 |
3.12975 |
| 3 |
Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge.
|
432.04 |
Square Meter |
0.057 |
24.62628 |
- |
- |
0.05 |
21.602 |
- |
- |
| 4 |
Painting (AR0920) : Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside)
|
469.34 |
Square Meter |
0.064 |
30.03776 |
- |
- |
- |
- |
0.054 |
25.34436 |
| 5 |
Flooring (AR0816) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge.
|
6.24 |
Square Meter |
0.216 |
1.34784 |
0.55 |
3.432 |
- |
- |
0.216 |
1.34784 |
| 6 |
Flooring (AR0817b) : Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge.
|
20.1 |
Square Meter |
0.325 |
6.5325 |
- |
- |
- |
- |
0.325 |
6.5325 |
| 7 |
Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.
|
53.04625 |
Square Meter |
0.17204301075269 |
9.1262365591398 |
- |
- |
- |
- |
0.18817204301075 |
9.9818212365591 |
| 8 |
Painting (AR0918g) : Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work .(Outside) - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside)
|
272.015 |
Square Meter |
0.11776344086022 |
32.033422365591 |
- |
- |
- |
- |
0.10776344086022 |
29.313272365591 |
| 9 |
Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge.
|
1.2 |
Quintal |
6.3976377952756 |
7.6771653543307 |
1.9685039370079 |
2.3622047244094 |
3.9370078740157 |
4.7244094488189 |
3.4448818897638 |
4.1338582677165 |
| 10 |
Painting (AR0901c) : Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge.
|
433.705 |
Square Meter |
0.053763440860215 |
23.31747311828 |
- |
- |
- |
- |
0.053763440860215 |
23.31747311828 |
| Total Qty |
167.63642739734 |
132.90887498815 |
13.113004724409 |
26.326409448819 |
| Rate Per Man Day |
462 |
612 |
512 |
562 |
| Total Amount |
77448.029457572 |
81340.231492746 |
6713.8584188976 |
14795.442110236 |
Total Labour Amount (in Rs.): 180297.56147945
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM174 |
BRM340 |
BRM028 |
BRM131 |
BRMMR0027 |
BRMMR0038 |
BRM140 |
BRM130 |
BRM129 |
BRM137 |
BRM141 |
BRM255 |
BRM252 |
BRM341 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) |
138 |
Sqm |
0.0076 |
1.0488 |
0.1074 |
14.8212 |
0.021 |
2.898 |
1 |
138 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. |
9.63 |
Sqm |
- |
- |
0.1375 |
1.324125 |
0.015 |
0.14445 |
1 |
9.63 |
1 |
9.63 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. |
432.04 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.8 |
345.632 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
Painting(AR0920) :.Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) |
469.34 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.125 |
58.6675 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 5 |
Flooring (AR0816) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. |
6.24 |
Sqm |
- |
- |
0.2737 |
1.707888 |
0.013 |
0.08112 |
- |
- |
1 |
6.24 |
- |
- |
- |
- |
1 |
6.24 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 6 |
Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. |
20.1 |
Sqm |
- |
- |
0.1375 |
2.76375 |
0.015 |
0.3015 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
20.1 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 7 |
Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. |
53.04625 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.054 |
2.8644975 |
0.125 |
6.63078125 |
- |
- |
- |
- |
- |
- |
| 8 |
Painting(AR0918g) :.Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work .(Outside) - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) |
272.015 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.125 |
34.001875 |
0.084 |
22.84926 |
- |
- |
| 9 |
Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. |
1.2 |
Qntl |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
1.2 |
| 10 |
Painting(AR0901c) :.Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. |
433.705 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.084 |
36.43122 |
- |
- |
| Total Qty |
1.0488 |
20.616963 |
3.42507 |
147.63 |
15.87 |
345.632 |
58.6675 |
6.24 |
20.1 |
2.8644975 |
6.63078125 |
34.001875 |
59.28048 |
1.2 |
| Rate Per Unit |
2047.912 |
534.912 |
352.89 |
662.3175001 |
8.5 |
30 |
249.64732 |
461.3175001 |
416.4375001 |
143.00732 |
205.64732 |
195.09732 |
125.80732 |
6206.132 |
| Total Amount |
2147.8501056 |
11028.260912256 |
1208.6729523 |
97777.932539763 |
134.895 |
10368.96 |
14646.1841461 |
2878.621200624 |
8370.39375201 |
409.6441106217 |
1363.6023935688 |
6633.674687475 |
7457.9183171136 |
7447.3584 |
Total Material Amount (in Rs.): 171873.96851743
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM174 |
BRM340 |
BRM028 |
BRM131 |
BRM140 |
BRM130 |
BRM129 |
BRM137 |
BRM141 |
BRM255 |
BRM252 |
BRM341 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) |
138 |
Sqm |
0.0076 |
1.0488 |
0.1074 |
14.8212 |
0.021 |
2.898 |
1 |
138 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Flooring (AR0817aa) :.Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. |
9.63 |
Sqm |
- |
- |
0.1375 |
1.324125 |
0.015 |
0.14445 |
1 |
9.63 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. |
432.04 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
Painting(AR0920) :.Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) |
469.34 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
0.125 |
58.6675 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 5 |
Flooring (AR0816) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. |
6.24 |
Sqm |
- |
- |
0.2737 |
1.707888 |
0.013 |
0.08112 |
- |
- |
- |
- |
1 |
6.24 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 6 |
Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. |
20.1 |
Sqm |
- |
- |
0.1375 |
2.76375 |
0.015 |
0.3015 |
- |
- |
- |
- |
- |
- |
1 |
20.1 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 7 |
Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. |
53.04625 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.054 |
2.8644975 |
0.125 |
6.63078125 |
- |
- |
- |
- |
- |
- |
| 8 |
Painting(AR0918g) :.Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work .(Outside) - Finishing wall with two coats weather coat paint of approved shade including one coat of oil bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) |
272.015 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.125 |
34.001875 |
0.084 |
22.84926 |
- |
- |
| 9 |
Iron Work(AR1704) :.Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. |
1.2 |
Qntl |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
1.2 |
| 10 |
Painting(AR0901c) :.Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality oil-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. |
433.705 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.084 |
36.43122 |
- |
- |
| Total Qty |
1.0488 |
20.616963 |
3.42507 |
147.63 |
58.6675 |
6.24 |
20.1 |
2.8644975 |
6.63078125 |
34.001875 |
59.28048 |
1.2 |
| Rate Per Unit |
0 |
0 |
375.25 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
| Total Amount |
0 |
0 |
1285.2575175 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total Royalty Amount (in Rs.): 1285.2575175
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Provision for PH Work @
Rs. 30000
|
Rs. 30000 |
| 2 |
Provision for EI Work @
Rs. 100000
|
Rs. 100000 |
| 3 |
Provision for Contingency @
Rs. 5000
|
Rs. 5000 |
| 4 |
Display Citizen Board @
Rs. 2000
|
Rs. 2000 |
| 5 |
Any Other Lumpsum @
Rs. 2771
|
Rs. 2771 |
Total Addition Component Amount (in Rs.): 139771
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 499999.32991522