| Stage | Officer | Date Started | Date Completed | Status |
|---|---|---|---|---|
| Case Record Opened | Binita Bijayeeni (BDO) | 18-02-2026 | 19-02-2026 | Approved |
| Estimate Preparation | Sasmita Hembram (AE / JE) | 19-02-2026 | 20-02-2026 | Approved |
| Technical Sanction | SWETAPADMA NANDA (AEE) | 20-02-2026 | 20-02-2026 | Approved |
| Administrative Approval | Binita Bijayeeni (BDO) | 20-02-2026 | 20-02-2026 | Approved |
| Work Order Issued | Binita Bijayeeni (BDO) | 07-03-2026 | 07-03-2026 | Generated |
| Execution In Progress | Prakash Taysam (AE / JE) | 07-03-2026 | 28-03-2026 | Approved |
| # | Name | Action | |
|---|---|---|---|
| 1 | Cover Page | View | Download |
| 2 | Sanction File | View | Download |
| 3 | Ordersheet | View | Download |
| 4 | Location Map | View | Download |
| 5 | Drawing | View | Download |
| 6 | Work site photo | View | Download |
| 7 | Quarry Document | View | Download |
| 8 | Estimate Cover Page | View | Download |
| 9 | Detail Estimate | View | Download |
| 10 | Abstract Estimate | View | Download |
| 11 | Estimation DPR | View | Download |
| 12 | Lead Statement | View | Download |
| 13 | Analysis | View | Download |
| 14 | Technical Sanction | View | Download |
| 15 | Administrative Approval | View | Download |
| 16 | Work Order | View | Download |