State: Odisha District: Balasore Block: Baleshwar Panchayat: Rainsuan
Work Code: OD/346/3299/275541/392549/00014697 (Construction of C.C Road from Sadashiba Mohapatra to Rukmani Samal. Ward no. 9 (Untied))
Project Category: Road
Financial Year: 2024-25 Execution Level: Rainsuan, G.P
Executing Agency: Panchayat Samiti, Baleshwar Proposal Date: 20-09-2024
Date of Commencement: - Date of Completion:
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: CC Road Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 0
Fund Sanction Amount (in Rs.): 100000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM045 BRM056 BRM029 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 6.66 Cum 2.29 15.2514 0.48 3.1968 0.96 6.3936 - - - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 5.18 Cum 3.23 16.7314 0.45 2.331 - - 0.9 4.662 - - - - - -
3 Earth Work (AR0101a1) :.Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 1.48 Cum - - - - - - - - - - - - - -
4 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 7.215 Cum - - - - - - - - 1 7.215 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 22.2 Sqm - - - - - - - - - - 0.00267 0.059274 0.126 2.7972
Total Qty 31.9828 5.5278 6.3936 4.662 7.215 0.059274 2.7972
Rate Per Unit 559.584 483.09 1833.27 2442.53 478.15 58696.742 352.762
Total Amount 17897.0631552 2670.424902 11721.195072 11387.07486 3449.85225 3479.190685308 986.7458664
Total Material Amount (in Rs.): 51591.546790908