State: Odisha |
District: Gajapati |
Block: Gosani |
Panchayat: Agarakhandi |
Work Code: OD/353/3357/117437/414711/00013361 (Repair and maintenance of Primary School at Badagan of GP-Agarakhandi)
Project Category: Building
Financial Year: 2022-23 |
Execution Level: Agarakhandi, G.P |
Executing Agency: Panchayat Samiti, Gosani |
Proposal Date: 22-11-2022 |
Date of Commencement: - |
Date of Completion: |
Scheme Name: 5th SFC Grant in Aid |
Scheme Component Name: Maintenance of Primary School Building |
Project Sub-Category: Elementary School |
Project Type: Repair and Maintenance |
Name of Executant: |
|
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 22574
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
1 |
Earth Work (AR0103a1) : Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per specification approved by the dept.
|
Cum |
3.174 |
319.837912 |
1015.165532688 |
2 |
Masonry Brick Work (AR0603c) : Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
Cum |
6.003 |
4854.866552064 |
29143.76391204 |
3 |
Concrete (AR0318a) : 4cm thick grading concrete (1:2:4) on roof slab with 12mm size hard granite chips (Hand Broken) - 4cm thick grading concrete (1:2:4) on roof slab with 12mm and down grade size hard granite chips (Hand Broken) for old work including hoisting and laying in position, compacting and curing for the proper period with cost conveyance, royalty, taxes of all materials, labor and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
Sqm |
75 |
683.4932149944 |
51261.99112458 |
4 |
miscellaneous (ARM286) : Supplying and fixing of 60mm thick cement concrete interlocking paver block of M-30 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 60mm thick cement concrete interlocking paver block of M-30 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge.
|
Sqm |
91.5 |
519.895 |
47570.3925 |
5 |
Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge.
|
Sqm |
26.1 |
158.1230517296 |
4127.0116501426 |
6 |
Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge.
|
Sqm |
26.1 |
229.129874216 |
5980.2897170376 |
7 |
Flooring (AR0817aa) : Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles.
|
Sqm |
15.75 |
1594.320138001 |
25110.542173516 |
8 |
Flooring (AR0817ab) : Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles.
|
Sqm |
2.4 |
1647.569762001 |
3954.1674288024 |
9 |
Painting (AR0918Ai) : Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge.
|
Sqm |
178 |
56.29770199 |
10020.99095422 |
Total Amount (in Rs.): 178184.31499303
LABOUR STATEMENT
Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Un-Skilled
|
Skilled
|
Highly-Skilled
|
Semi-Skilled
|
452 |
552 |
602 |
502 |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
1 |
Earth Work (AR0103a1) : Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per specification approved by the dept.
|
3.174 |
Cubic Meter |
0.7006 |
2.2237044 |
- |
- |
- |
- |
- |
- |
2 |
Masonry Brick Work (AR0603c) : Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
6.003 |
Cubic Meter |
2.96 |
17.76888 |
- |
- |
1.05 |
6.30315 |
0.35 |
2.10105 |
3 |
Concrete (AR0318a) : 4cm thick grading concrete (1:2:4) on roof slab with 12mm size hard granite chips (Hand Broken) - 4cm thick grading concrete (1:2:4) on roof slab with 12mm and down grade size hard granite chips (Hand Broken) for old work including hoisting and laying in position, compacting and curing for the proper period with cost conveyance, royalty, taxes of all materials, labor and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
75 |
Square Meter |
1.008 |
75.6 |
- |
- |
- |
- |
0.165 |
12.375 |
5 |
Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge.
|
26.1 |
Square Meter |
0.12 |
3.132 |
- |
- |
0.14 |
3.654 |
- |
- |
6 |
Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge.
|
26.1 |
Square Meter |
0.24 |
6.264 |
- |
- |
0.16 |
4.176 |
- |
- |
7 |
Flooring (AR0817aa) : Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles.
|
15.75 |
Square Meter |
0.325 |
5.11875 |
0.76 |
11.97 |
- |
- |
0.325 |
5.11875 |
8 |
Flooring (AR0817ab) : Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles.
|
2.4 |
Square Meter |
0.325 |
0.78 |
0.76 |
1.824 |
- |
- |
0.325 |
0.78 |
9 |
Painting (AR0918Ai) : Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge.
|
178 |
Square Meter |
0.043 |
7.654 |
- |
- |
- |
- |
0.036 |
6.408 |
Total Qty |
118.5413344 |
14.13315 |
26.7828 |
13.794 |
Rate Per Man Day |
452 |
552 |
602 |
502 |
Total Amount |
53580.6831488 |
7801.4988 |
16123.2456 |
6924.588 |
Total Labour Amount (in Rs.): 84430.0155488
MATERIAL STATEMENT
Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM006 |
BRM340 |
BRM028 |
BRM057 |
BRM064 |
BRM029 |
BRMM286 |
BRM131 |
BRMMR0027 |
BRM132 |
CON026 |
BRM255 |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
1 |
Earth Work (AR0103a1) :.Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per specification approved by the dept. |
3.174 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
2 |
Masonry Brick Work (AR0603c) :.Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
6.003 |
Cum |
400 |
2401.2 |
0.672 |
4.034016 |
0.28 |
1.68084 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
3 |
Concrete (AR0318a) :.4cm thick grading concrete (1:2:4) on roof slab with 12mm size hard granite chips (Hand Broken) - 4cm thick grading concrete (1:2:4) on roof slab with 12mm and down grade size hard granite chips (Hand Broken) for old work including hoisting and laying in position, compacting and curing for the proper period with cost conveyance, royalty, taxes of all materials, labor and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
75 |
Sqm |
- |
- |
0.1287 |
9.6525 |
0.018 |
1.35 |
0.018 |
1.35 |
0.018 |
1.35 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
4 |
miscellaneous(ARM286) :.Supplying and fixing of 60mm thick cement concrete interlocking paver block of M-30 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 60mm thick cement concrete interlocking paver block of M-30 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. |
91.5 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.05 |
4.575 |
1 |
91.5 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
5 |
Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. |
26.1 |
Sqm |
- |
- |
0.0358 |
0.93438 |
0.015 |
0.3915 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
6 |
Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. |
26.1 |
Sqm |
- |
- |
0.043 |
1.1223 |
0.018 |
0.4698 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
7 |
Flooring (AR0817aa) :.Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles. |
15.75 |
Sqm |
- |
- |
0.1375 |
2.165625 |
0.015 |
0.23625 |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
15.75 |
1 |
15.75 |
- |
- |
- |
- |
- |
- |
8 |
Flooring (AR0817ab) :.Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles. |
2.4 |
Sqm |
- |
- |
0.1375 |
0.33 |
0.015 |
0.036 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
2.4 |
1 |
2.4 |
0.1375 |
0.33 |
- |
- |
9 |
Painting(AR0918Ai) :.Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. |
178 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.075 |
13.35 |
Total Qty |
2401.2 |
18.238821 |
4.16439 |
1.35 |
1.35 |
4.575 |
91.5 |
15.75 |
18.15 |
2.4 |
0.33 |
13.35 |
Rate Per Unit |
5.36398 |
324.872 |
417.99 |
1426.3 |
1191.31 |
413.05 |
485.28 |
662.3175001 |
8.5 |
706.9975001 |
0 |
195.09732 |
Total Amount |
12879.988776 |
5925.282255912 |
1740.6733761 |
1925.505 |
1608.2685 |
1889.70375 |
44403.12 |
10431.500626575 |
154.275 |
1696.79400024 |
0 |
2604.549222 |
Total Material Amount (in Rs.): 85259.660506827
ROYALTY STATEMENT
Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM006 |
BRM340 |
BRM028 |
BRM057 |
BRM064 |
BRM029 |
BRM131 |
BRM132 |
BRM255 |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
1 |
Earth Work (AR0103a1) :.Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m - Earthwork in stoney earth and gravels mixed with stone and boulder not exceeding 0.014cum in volume within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per specification approved by the dept. |
3.174 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
2 |
Masonry Brick Work (AR0603c) :.Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
6.003 |
Cum |
400 |
2401.2 |
0.672 |
4.034016 |
0.28 |
1.68084 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
3 |
Concrete (AR0318a) :.4cm thick grading concrete (1:2:4) on roof slab with 12mm size hard granite chips (Hand Broken) - 4cm thick grading concrete (1:2:4) on roof slab with 12mm and down grade size hard granite chips (Hand Broken) for old work including hoisting and laying in position, compacting and curing for the proper period with cost conveyance, royalty, taxes of all materials, labor and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
75 |
Sqm |
- |
- |
0.1287 |
9.6525 |
0.018 |
1.35 |
0.018 |
1.35 |
0.018 |
1.35 |
- |
- |
- |
- |
- |
- |
- |
- |
4 |
miscellaneous(ARM286) :.Supplying and fixing of 60mm thick cement concrete interlocking paver block of M-30 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 60mm thick cement concrete interlocking paver block of M-30 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. |
91.5 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.05 |
4.575 |
- |
- |
- |
- |
- |
- |
5 |
Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. |
26.1 |
Sqm |
- |
- |
0.0358 |
0.93438 |
0.015 |
0.3915 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
6 |
Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. |
26.1 |
Sqm |
- |
- |
0.043 |
1.1223 |
0.018 |
0.4698 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
7 |
Flooring (AR0817aa) :.Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles. |
15.75 |
Sqm |
- |
- |
0.1375 |
2.165625 |
0.015 |
0.23625 |
- |
- |
- |
- |
- |
- |
1 |
15.75 |
- |
- |
- |
- |
8 |
Flooring (AR0817ab) :.Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Vitrified floor tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm Coloured /Printed series(Homogeneous) in in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including rubbing and polishing complete including cost of precast tiles. |
2.4 |
Sqm |
- |
- |
0.1375 |
0.33 |
0.015 |
0.036 |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
2.4 |
- |
- |
9 |
Painting(AR0918Ai) :.Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. |
178 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.075 |
13.35 |
Total Qty |
2401.2 |
18.238821 |
4.16439 |
1.35 |
1.35 |
4.575 |
15.75 |
2.4 |
13.35 |
Rate Per Unit |
0.16025 |
0 |
279.25 |
269.5 |
269.5 |
279.25 |
0 |
0 |
0 |
Total Amount |
384.7923 |
0 |
1162.9059075 |
363.825 |
363.825 |
1277.56875 |
0 |
0 |
0 |
Total Royalty Amount (in Rs.): 3552.9169575
ADDITION COMPONENT
S/N |
Item Name |
Amount (in Rs.) |
1 |
Provision for Contingency @
1%
|
Rs. 1781.8431499303 |
2 |
Display Citizen Board @
Rs. 2500
|
Rs. 2500 |
3 |
Any Other Lumpsum @
Rs. 16786
|
Rs. 16786 |
Total Addition Component Amount (in Rs.): 21067.84314993
DEDUCTION COMPONENT
Sl.No. |
Item Name |
Amount (in Rs.) |
No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 199252.15814296